Received Robert's weekly progress report on Moscone.
1...Summary/Objective
..............
Click here to comment!
CONTACTS
0201 - Gensler/Michael Willis/Kwan Henmi 415 433 3700 fax 415 627 3700
020101 - Mr. Robert Rudeen; Architect
020102 - Kwan Henmi Architects
020103 - Interior Design/Documentation
SUBJECTS
Project Work Summary
Policy/Procedures, Project Work Summary Form
Document Management
Forms Management, Project Work Summary
0806 - ..
0807 - Summary/Objective
0808 -
080801 - Follow up ref SDS 13 3216.
080802 -
080803 - Received ref DIT 1 0000 which is Robert's weekly progress report and
080804 - diary on Moscone for period ending 981023.
080805 -
080806 - [On 981030 received next report. ref SDS 16 4602]
080807 -
080808 - This is part of his work practice along with the weekly work plan
080809 - system, and his binder with scheduled tasks and notes of daily
080810 - information, also discussed yesterday. ref SDS 13 3234
080811 -
080812 - Created an HTML format so he can get it from the document log system,
080813 - developed beginning on 981015. ref SDS 2 5292
080814 -
080815 - Decided to make a formal document because it has a date and is in the
080816 - vein of a report. For convenience addressed it from Robert from the
080817 - Moscond project, to Kwan Henmi and used Denis. Could just as well
080818 - used Bill or Robert himself, since this is really a memo to file.
080819 -
080820 - He uses it as a planning tool. Writing out what has been
080821 - accomplished, forces consideration of what needs to be done, which is
080822 - the idea of the SDS program, per analysis on 981027, ref SDS 13 3216