THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700
S U M M A R Y
DIARY: October 1, 1997 07:08 AM Wednesday;
Rod Welch
Called Tom at Corps of Engineers on cost savings analysis.
1...Summary/Objective
.....District Operation Savings
.....Detailed Cost Savings
.....Navy Sewer Line
.....Partnering Supported by Communiction Metrics Yields Savings
.....Soft to Hard Polygon Change
.....Todd/Schnitzer Wing Contaminated Materials Claim
.....Mud Bucket, Weekly Planning, Completion Schedule Update
.....Progress Meetings
.....Rework
.....Litigation
..............
Click here to comment!
CONTACTS
0201 - Corps of Engineers, SFD 415 977 8400 fax 8483
020101 - Mr. Thompson F. Keesling, Architect; Assistant Chief =415 977 8473
020102 - Construction Operations Division =415 977 8480
0202 - Corps of Engineers, SFD 415 977 8400 fax 8483
020201 - Mr. Max R. Blodgett, II, P.E., L.S.
020202 - Chief =415 977 8444; Construction Operations Division =415 977 8480
SUBJECTS
COE Evaluation Communication Metrics
Analysis, Review, Research
Institutionalize Communication Metrics
CE HQ Evaluation
Calculate Risk Management Exposure NPV
1007 -
1007 - ..
1008 - Summary/Objective
1009 -
100901 - Follow up ref SDS 42 0000, ref SDS 41 5180.
100902 -
100903 - Received a proposed letter from Tom to Jim Jones. Developed some
100904 - figures below for review by Tom that provide a format to evalute cost
100905 - savings per Jim's request on 970926, ref SDS 40 0552. Transferred the
100906 - analysis in this record to the file at ref OF 1 2435.
100907 -
100908 - [Completed analysis at ref SDS 44 5562.]
100910 - ..
100911 - [See Tom's edits at ref SDS 50 3994.]
100913 - ..
100914 - [See submission of final version to Jim Jones, ref SDS 53 2979.]
100916 - ..
100917 - [On 971011 added edits to correlate limited span of attention to
100918 - span of management, ref SDS 54 1221.]
100920 - ..
1010 -
1011 -
1012 - Discussion
1013 - ..
101301 - Tom said he sent an email yesterday. Since I did not get it, he
101302 - will re-submit.
101304 - ..
101305 - We discussed the possibility of Tom talking to Merry Goodenough about
101306 - estimating the savings to the government on the claims by Dutra, based
101307 - on the SDS record prepared to-date. I explained the idea of crafting
101308 - the record as an appellate brief, and so it should directly assist the
101309 - parties in resolving issues discussed in the record.
101311 - ..
101312 - It may be that COE counsel have not yet had the opportunity to review
101313 - the record in sufficient degree.
101315 - ..
101316 - Tom seemed to indicate he will try to discuss this with Merry.
101317 -
101318 -
101320 - ..
1014 -
1015 -
1016 - 0827 received Tom's letter
1017 -
101701 - Received ref DRT 1 0000 from Tom, per above discussion, and our
101702 - meeting on Monday, ref SDS 42 0000. Tom proposes the following
101703 - message to Jim:
101704 -
101705 - It is very dificult to determine the cost savings for the
101706 - application of Communications Metrics within the district
101707 - organization without a longer test period for evaluation.
101709 - ..
101710 - However, I feel confident that if there was a format that you
101711 - wanted the information presented in that that might help focus my
101712 - efforts to provide the cost information. I am sure that when
101713 - Project Management was integrated into the Corps of Engineers that
101714 - there was a cost benefit part of the decision making process and a
101715 - similar one done for the decision to utilize the Resident
101716 - Management System. Again if those could be furnished to me it
101717 - would help in me preparing the cost analysis that you requested
101718 - previously and which I had provided a narrative response earlier.
101719 -
101720 - [On 971001 prepared memo to use Tom's ideas in memo to Jim
101721 - Jones. ref SDS 45 0000]
101723 - ..
101724 - Analysis:
101725 -
101726 - 1. If Jim is really interested in this iniative, it does not
101727 - matter much what we say.
101728 -
101729 - 2. If he is getting tired of Communication Metrics, and other
101730 - stuff has his attention, it does not matter what we say.
101732 - ..
101733 - 3. If we have a shot, we want to be positive, present specific
101734 - areas of savings and ask him how he wants it formatted.
101736 - ..
101737 - Since we have already acknowledged it is difficult to estimate
101738 - savings exactly, and Jim has made the same point, maybe we can
101739 - avoid re-stating it again, and simply identify areas of
101740 - savings based on his ideas.
101741 -
101742 - ..
101743 - Developed following analysis of cost savings from Communication
101744 - Metrics, per Jim's request at ref SDS 40 4225, and put it in the file
101745 - ref OF 1 2435, mostly as the "Attachment" at ref OF 1 1835. It
101746 - reflects Max Wideman's suggestion to focus on cost savings as the best
101747 - measure of added value, ref SDS 19 2294. Developed measurement of
101748 - cost savings by reducing "rework," which Max cited at ref SDS 21 1817.
101749 -
101750 - [See edits next day at ref SDS 46 line 160.]
101752 - ..
101753 - Dear Jim,
101755 - ..
101756 - Per discussions last Friday and my email on Sep 4, here is an
101757 - estimate of savings from Communication Metrics. I am not sure
101758 - about differentiating project from operations costs, since the
101759 - latter are calculated as a multiplier of project budgets. Seems
101760 - like if we save on project budgets, then savings will acrue to
101761 - operational budgets based on the multiplier.
101763 - ..
101764 - In any case, savings on operations can be estimated based on the
101765 - common value of communication for operations and projects. In
101766 - other words the benefit of Communication Metrics to weekly
101767 - progress meeetings, for example, would be similar for District
101768 - staff meetings. Organizing the record and analysing alignment of
101769 - project decisions, would be valuable for operations, as discussed
101770 - in the notes of your telecon with Welch on Sep 26, ref SDS 39 line
101771 - 263. We can therefore estimate operation budget savings by
101772 - calculating savings on the Oakland Harbor project, and applying
101773 - an adjusted percentage to the cost of operations.
101775 - ..
101776 - This method results in the following estimated savings:
101777 -
101778 - Original Estimated
101779 - Budgets Adds Final
101781 - ..
101782 - Direct cost of Oakland Harbor was: $42M 10 $52M
101784 - ..
101785 - COE Supervision and Admin was 8%: 3M 1 4M
101786 -
101787 - Total estimated final cost............................ $56M
101788 -
101790 - ..
101791 - Cost Avoidance
101792 -
101793 - Navy Sewer Line .4M
101794 - Soft to Hard Polygon Change 1.0M
101795 - Todd/Schnitzer Wing
101796 - Contaminated Materials Claim 2.0M
101797 - -----
101798 - Total Cost Avoidance.............3.4M ................ 3.4M
101800 - ..
101801 - Cost Savings on Budgets
101802 -
101803 - NSL 30K
101804 - Soft to Hard Polygon 60K
101805 - Other issues 68K
101806 - Re-work 170K
101807 - -----
101808 - 328K 328K
101810 - ..
101811 - Progress Meetings for 2 years $117K
101812 - Re-work " " " 1,054K
101813 - Litigation " " " 780K
101814 - ---------
101815 - 1,951 1,951K
101816 - --------
101817 - Total savings on budgets................ 2,279K 2.3
101818 -
101819 - ------
101820 - Total savings on project............................... $5.7M
101821 -
101823 - ..
101824 - Communication Metrics Cost for 2 years
101825 -
101826 - 200K x 2 - 50K 400K
101828 - ..
101829 - Welch made special effort on Oakland to demonstrate
101830 - validity of Communication Metrics. Allow additional
101831 - budget for normal staffing
101832 -
101833 - 150K
101834 - -------
101835 - Total cost of savings............. $550K .6M
101837 - ..
101838 - ROI......................................................... 9
101839 -
101841 - ..
101842 - District Operation Savings
101843 -
101844 - Estimate 5.7M savings on $56M adjusted project is approximately
101845 - 10% savings.
101846 -
101847 - Assume Oakland Harbor was unusual due to bankruptcy of contractor,
101848 - and so savings was larger than typical project, so estimate 6%
101849 - savings on typical projects. District operations may be less prone
101850 - to communication errors for the reasons in the letter to Jim on
101851 - 970926, ref SDS 40 line 280. A conservative estimate is 4% savings
101852 - on District operations. The District budget is approximately $65M
101853 - per year. $20M is non-project outlay. Savings then would be:
101854 -
101855 - [See further analysis leading to 6% estimate, ref SDS 49 line
101856 - 170.]
101857 -
101858 - .04 x 20M = $800K
101860 - ..
101861 - Estimated cost would be 200K
101863 - ..
101864 - The record on Oakland constructon operations indicates there is a
101865 - good chance savings can increase by using Communication Metrics
101866 - from the beginning of a project through the design phase.
101867 -
101869 - ..
101870 - Detailed Cost Savings
101871 -
101872 - This has two components:
101873 -
101874 - 1. Cost Avoidance, which is speculative
101875 -
101876 - 2. Cost Savings on Budgets which reflects direct
101877 - reduction in level of effort.
101878 -
101880 - ..
101881 - Navy Sewer Line
101882 -
101883 - Marc McGovern, Construction Manager on Oakland reported
101884 - Communication Metrics identified a solution to the Navy Sewer
101885 - Line problem, ref DRP 2 line 834. Over many months the
101886 - Contractor identified a potential change due to alleged defects
101887 - in contract drawings. At the Progress Meeting on 961015, ref
101888 - SDS 45 line 600, the contractor submitted a proposal for:
101889 -
101890 - Extra Cost to stabalize slope per Dwgs. $373K
101892 - ..
101893 - Analysis showed a possible basis for a changed condition, but
101894 - Communication Metrics discovered alignment in the underlying
101895 - record which had been overlooked that eliminated this cost.
101896 - The contractor realized improved earnings at no increase to the
101897 - Corps of Engineers.
101899 - ..
101900 - Corps of Engineers staff invested approximatley 100 hours in
101901 - administering this matter in the three months prior to
101902 - application of Communication Metrics. It is estimated that at
101903 - least another 100 hours would have been expended by the Corps
101904 - but for the solution identified by Communication Metrics.
101905 -
101906 - 200 hours at $150/Hr 30K
101907 -
101909 - ..
101910 - Partnering Supported by Communiction Metrics Yields Savings
101911 -
101912 - Saving $400K and improving the Contractor's income posture
101913 - advances partnering objectives.
101914 -
101916 - ..
101917 - Soft to Hard Polygon Change
101918 -
101919 - From approximately October 1995 to March 1996 the contractor
101920 - notified the Corps of Engineers it had encountered hard
101921 - material at various locations where the drawings showed the
101922 - material was soft.
101924 - ..
101925 - A series of RFPs were issued.
101927 - ..
101928 - The contractor responded to all RFPs at once on 960730, seeking
101929 - a total of approximately $7M extra payment.
101931 - ..
101932 - The Corps maintained the contractor bid the same unit price to
101933 - dredge in areas shown as "hard" as it bid to dredge areas shown
101934 - as "soft," and so argued additional payment was not warranted.
101936 - ..
101937 - A major source of communication arose over the form of the
101938 - original RFPs which requested a lump sum price for work that
101939 - was bid as unit price. The form of the language became so
101940 - embroiled as to cause the cost-sharing sponsor to argue on
101941 - behalf of the contractor's cost request, despite the fact that
101942 - the cost-sharing sponsor regularly voiced opposition to the
101943 - contractor's claim.
101945 - ..
101946 - Communication Metrics was begun in September 1996. Within a
101947 - month or so it was applied to the Soft to Hard Polygon claim.
101949 - ..
101950 - Analysis showed:
101951 -
101952 - 1. A number of mathamatical and contractual errors in the
101953 - contractor's submission.
101954 -
101955 - 2. Lack of alignment between the record of samples taken in
101956 - the field that spawned the RFPs, and the sweeping scope
101957 - of the RFPs which converted an entire polygon from soft
101958 - to hard, rather than merely acknowledge, that a
101959 - particular polygon may contain some material that is
101960 - harder than it is soft.
101962 - ..
101963 - 3. Evident support for the Corps of Engineer's position
101964 - that no increase in payment was warranted. A strategic
101965 - adjustment was recommended to withdraw the 3 or 4
101966 - original RFPs and combine them into a single RFP #19
101967 - with an express requirement to submit a unit price.
101969 - ..
101970 - This strategy transcended the hours, days and weeks of
101971 - argument between the Contracting Officer's team and the
101972 - contractor about application of FAR regulations.
101973 - ..
101974 - Total savings is approximately $7M. We will estimate
101975 - savings resulting from the contribution of Communication
101976 - Metrics as:
101977 -
101978 - = $1M
101980 - ..
101981 - Additionally, approximately 400 hours was saved by the
101982 - strategy of combining the RFPs. This is computed as a
101983 - week of the project team, as shown below:
101984 -
101985 - 400 x $150 = $60K
101986 -
101988 - ..
101989 - Todd/Schnitzer Wing Contaminated Materials Claim
101990 -
101991 - The contractor encountered underwater debris in an area of the
101992 - work. Communication Metrics aligned the record of conditions
101993 - found in the field with the notice by the contractor and with
101994 - contract provisions. This supported a determination that a
101995 - changed condition existed. An RFP was crafted to enable the
101996 - work to procede so that payment was equitable to the contractor
101997 - and to the Corps of Engineers.
101999 - ..
102000 - The contractor refused to perform the RFP, claiming later events
102001 - established that contaminated materials existed in the
102002 - Todd/Schnitzer wings which required special handling at increased
102003 - cost. Due to communication mixups from not applying Communication
102004 - Metrics RFP 20 was rescinded by the District, relieving the
102005 - contractor from a direction to perform the work. Eventually, the
102006 - contractor claimed $15M in extra payment was needed to perform
102007 - additional debris removal work, estimated by the government at
102008 - approximately $500K.
102009 - ..
102010 - Communication Metrics tracked conflicting promises and
102011 - unsubstantiated contentions by the contractor claiming it had
102012 - commissioned tests proving contamination. Since this matter
102013 - remains open, for purposes of this estimate the savings
102014 - attributable to Communication Metrics is approximately:
102015 -
102016 - = $2M
102017 -
102019 - ..
102020 - Mud Bucket, Weekly Planning, Completion Schedule Update
102021 -
102022 - During the short period Communication Metrics was used, it
102023 - revealed the contractor was not performing a large number of
102024 - requirements. Problems that were being worked by Corps of
102025 - Engineers staff were shown to be contractor responsibilities. A
102026 - prominent example was the meeting on 961213 where the contractor
102027 - presented an updated schedule with many pages of backup support.
102028 - Communication Metrics revealed the backup did not support
102029 - contractor projections and that the contractor either with
102030 - deliberation or inadvertance misrepresented and concealed from the
102031 - Corps of Engineers at that meeting on 961213, its true intentions.
102033 - ..
102034 - For this order of magnitude estimate, rather than explain every
102035 - matter, we estimate savings as follows:
102036 -
102037 - 15 issues x 40 hours per issue
102038 -
102039 - 450 x $150 = 68K
102041 - ..
102042 - Progress Meetings
102043 -
102044 - As a result of contractor difficulties leading to major claims by
102045 - the Contractor, the Corps of Engineers began staffing weekly
102046 - Progress Meetings with 10 to 15 people from Engineering,
102047 - Contracting, Construction, Environmental, etc.
102049 - ..
102050 - This attendance posture was intended to improve "communication"
102051 - among affected staff whose work may have been impacted by
102052 - various issues. It may have been intended to demonstrate
102053 - heightened scrutiny and concern by the Corps of Engineers in
102054 - improving performance by the Contractor.
102056 - ..
102057 - Communication Metrics demonstrated this level of attendance was
102058 - unnecessary. Better understanding was achieved through the
102059 - meeting notes, and it was maintained through the record, rather
102060 - than become distorted by constant recall from each attendee.
102061 - Follow up was more rigorous and effective using the Action Item
102062 - system endemic to SDS that supports Communication Metrics. As a
102063 - result Chief Con Ops was able to order attendance restricted to
102064 - RE, PE and the Communication Manager. The PM attended on
102065 - occassion, however, as Herb Cheong's memo states, research
102066 - prior to meetings and post meeting briefings by the
102067 - Communication Manager ensured more thorough and productive
102068 - meetings, ref DRP 2 line 736.
102070 - ..
102071 - A conservative estimate of cost savings assumes avoid 5 people
102072 - for 1.5 hours per meeting for the 2 year duration of the job.
102073 -
102074 - 5 x 1.5 x 52 x 2 = 780 hours x $150 = $117K
102076 - ..
102077 - The more important contribution of Communication Metrics is
102078 - making meetings productive, as discussed under re-work.
102079 -
102081 - ..
102082 - Rework
102083 -
102084 - Authorities cited on 930216 recognize "rework" is a major source
102085 - of cost escalation, ref SDS 3 4633, and on 970713. ref SDS 21
102086 - 1817. Costs arise from errors of induction due to limited span of
102087 - attention from analysis of organic subject structure on 910221,
102088 - ref SDS 2 RR5I, and review of Jeremy Campbell's book, "The
102089 - Improbable Machine" on 900303, ref SDS 1 5555, and increase over
102090 - time as the information base tends toward entropy, per study by
102091 - U.S Air Force Institute of Technology, see review on 970707,
102092 - ref SDS 20 0108, and letter on 970929, ref DIP 8 0001, confirming
102093 - discussions on 970926, ref SDS 40 3377. The meeting with Intel on
102094 - 970728 shows the cause of rework. ref SDS 25 4818
102096 - ..
102097 - Landauer's paper on human cognition reviewed on 960324 explains
102098 - complexity of subjects. ref SDS 7 8566
102099 -
102100 - [On 971002 did more work on idea, ref SDS 46 2464.]
102101 -
102102 - [See example from Web project on rework caused by lack of
102103 - notice. ref SDS 55 1840]
102105 - ..
102106 - [On 970910 executives at major financial institution do not
102107 - have enough time to think. ref SDS 35 3479 On 980416 firm
102108 - reported reduced earnings due to increased operations costs.
102109 - ref SDS 57 4269]
102111 - ..
102112 - [On 971008 received report from USACE covering these ideas.
102113 - ref SDS 53 1273
102115 - ..
102116 - [On 980412 CBS News 60 Minutes broadcast a program segment on
102117 - information overload causing widespread problems. ref SDS 56
102118 - 2085]
102120 - ..
102121 - [On 980511 report U.S. business productivity declined and
102122 - unit labor costs rose dramatically. ref SDS 58 0000.]
102124 - ..
102125 - [On 980630 article on calculating cost benefit of knowledg
102126 - tools. ref SDS 60 0606]
102128 - ..
102129 - The more common description of "rework" is "problem handling"
102130 - discussed in a PM Network article reviewed on 951212, ref SDS 6
102131 - 4433 and when that fails, costs are either absorbed as "Murphy's
102132 - Law" or litigation expense is incurred, ref SDS 3 line 267. This
102133 - estimate for rework looks only at costs that are absorbed, since
102134 - litigation expense is considered separately.
102136 - ..
102137 - "Rework" in management reflects inability to attain closure on
102138 - issues, as cited in the PMI presentation on 970910, ref SDS 35
102139 - line 464, due to conflicts between decisions and the record that
102140 - leak out over weeks and months.
102142 - ..
102143 - A common example are meetings where understandings among attendees
102144 - are argued at length, per ref SDS 3 line 241. Decisions are
102145 - developed, reviewed, changed and changed again due to lack of
102146 - alignment with controlling authority, e.g., the record of
102147 - performance, contract provisions, policies, regulations, laws.
102148 - Communication increases exponentially, new players come on the
102149 - scene and no one knows original objectives because of a limited
102150 - span of attention in human biology, ref SDS 32 line 224, which was
102151 - described as "not having enough time to think" in the PMI
102152 - presentation on 970910, ref SDS 35 line 468. Of course people are
102153 - thinking all the time. The real problem is that the number of
102154 - things to think about exceeds the span of attention.
102155 -
102156 - [Stanford closed its Project Office manned by best of best
102157 - ref SDS 47 line 104.]
102159 - ..
102160 - Acrimony replaces thoughtful dialog, progress declines, posturing
102161 - and belligerence permeate every aspect of communication, per
102162 - experience at Chips with Lockheed, ref SDS 9 line 1022, and Intel,
102163 - ref SDS 14 line 109, and on need for psychologists, ref SDS 5 line
102164 - 137.
102166 - ..
102167 - Communication Metrics reduces rework in two fundamental ways:
102168 -
102169 - 1. It aligns understandings and therefore decisions with
102170 - the complete record, including controlling authority.
102171 -
102172 - This alignment process avoids the steady drip, drip of new
102173 - and unforseen correlations that prevent closure under
102174 - conventional practice because people to do not have enough
102175 - time to think of all of the factors that impact success,
102176 - ref SDS 35 line 476. Technology makes it possible to apply
102177 - expertise to identify more controlling factors
102178 - prospectively, rather than wait to discover them through
102179 - trial and error.
102181 - ..
102182 - 2. Action Items are scheduled and maintain visibility
102183 - linked to original reasoning and factual basis, so that
102184 - needed action is not forgotten by the arrival of new
102185 - tasks each day.
102187 - ..
102188 - On Oakland, there are approximately 10 key players:
102189 -
102190 - Hrs/Week
102191 - Planned Actual
102192 -
102193 - Project Engineer 40 45
102194 - Inspector Supervisors 80 90
102195 - Inspectors AE 240 250
102196 - Resident Engineer 5 20
102197 - Construction Manager 10 22
102198 - Chief of Construction Operations 2 6
102199 - Asst. Chief Con Ops 4 15
102200 - Projct Manager 5 12
102201 - Design Engineer 5 10
102202 - Chief of Engineering 2 5
102203 - Contract Officer 3 10
102204 - Contract Specialist 2 5
102205 - Environmental Engineer 2 5
102206 - ----- -----
102207 - Total hours per week................. 396 495
102209 - ..
102210 - Actual time to manage the work is 25% above budgeted time, but for
102211 - District staff the investment is 200% - 300% greater which causes
102212 - significant reduced attention to other matters, snowballing
102213 - reduced effectiveness on everything. [per suggestion by Morris on
102214 - 971007, ref SDS 51 7005] This condition leads to cursory
102215 - treatment and escalating reliance on "guess and gossip" cited in
102216 - the Corps of Engineers report, ref DRP 2 3649, and in the NWO
102217 - paper. ref OF 3 5821
102219 - ..
102220 - The amount of time lost due to rework can be calculated from the
102221 - difference between the typical agenda prepared for meetings which
102222 - reflects subjects that are recognized as material to performance,
102223 - and the actual number of subjects "discovered" and tracked by
102224 - Communication Metrics, per meeting with Intel on 970728,
102225 - ref SDS 25 3002, and analysis on 970726, ref SDS 24 6639. A second
102226 - factor is the number of links (citations, references) that align
102227 - understandings in the record, since this represents specific
102228 - conflicts that require corrections.
102230 - ..
102231 - The agenda for the 961001 Progress Meeting had 10 substantive
102232 - items, ref DIP 3 line 19, per ref SDS 10 8388. This is a typical
102233 - agenda for weekly progress meeting.
102234 -
102235 - [See telecon with Bill DeHart on 971005, ref SDS 48 4921.]
102236 -
102237 - [See support from telecon with Max Wideman, ref SDS 51 5920.]
102239 - ..
102240 - Communication Metrics actually tracked the following factors at
102241 - weekly progress meetings (using new SDS utility, ref SDS 26 0001):
102242 -
102243 - Partici- Sub- Cita- Action
102244 - Date Time pants Words jects tions Items
102245 -
102246 - 961001 1000 19 1125 40 10 7
102247 - 961009 1300 19 1861 47 29 9
102248 - 961015 1000 15 2193 61 32 7
102249 - 961022 1000 21 2974 57 24 7
102250 - 961029 1000 15 2898 60 44 12
102251 - 961105 1000 14 3671 65 36 11
102252 - 961112 1000 14 4553 56 91 16
102253 - 961119 1000 13 4377 48 93 4
102254 - 961126 1000 12 2811 39 59 11
102255 - 961203 1000 11 1416 27 30 2
102256 - 961209 1330 4 3162 31 69 14
102257 - 961219 1000 4 2521 28 48 9
102258 - 961230 1330 4 1956 32 37 6
102259 - 970106 1200 6 2626 6 32 15
102260 - 970106 1400 6 1753 22 27 6
102261 - ----- ----- ----
102262 - 619 661 136
102263 -
102265 - ..
102266 - Since, as noted, common practice identifies about 10 subjects
102267 - per meeting, then for these 15 meetings, a total of 150
102268 - subjects would have been worked. Communication Metrics
102269 - identified 619 or 469 more. This reflects additional rigor of
102270 - Communication Metrics that identifies correlations and
102271 - implications so that rework is avoided, per meeting with
102272 - Intel, ref SDS 25 5920.
102274 - ..
102275 - Citations should be added to this amount because they
102276 - reflect alignment which is impossible under conventional
102277 - management and leads directly to re-work.
102278 -
102279 - Additional Subjects 469
102280 - Citations (alignment) 661
102281 - -----
102282 - 1130
102284 - ..
102285 - Assume each missed subject and alignment results in one (1)
102286 - hour of re-work. Therefore, Communication Metrics produced
102287 - savings of:
102288 -
102289 - 1130 x $150 = $170K
102291 - ..
102292 - Total savings on project for 2 year job.
102293 -
102294 - 3 x 4 x 2 x 170 = 4,080
102295 -
102296 - Assume normal bell curve and that period when Communication
102297 - Metrics was applied was at or near peak activity, so that
102298 - actual savings is only 30% of peak rate.
102299 -
102300 - .3 x 4080 = 1,224K
102302 - ..
102303 - Average savings per week over 3 months
102304 -
102305 - $170/12 = $14K
102307 - ..
102308 - The weekly savings from Communication Metrics correlates
102309 - with increased expense for Corps of Engineers staff that
102310 - was otherwise required to perform "problem handling" that
102311 - escalated to putting out fires that developed on Oakland.
102312 -
102313 - 90 x 150 = $14K
102315 - ..
102316 - A major advantage to using Communication Metrics rather
102317 - than increasing District staff time, besides freeing staff
102318 - for their normal duties, is that Communication Metrics
102319 - produces a record that is constant that can be used over
102320 - and over again without the evolution in understandings when
102321 - "too many cooks" get embroiled in the "kitchen."
102322 -
102324 - ..
102325 - Litigation
102326 -
102327 - Jim Stout, former District counsel who specialized in contract
102328 - litigation, examined Communication Metrics work product on the
102329 - Oakland Harbor project. In a meeting on 961015 Jim advised the
102330 - Contracting Officer, Tom Benero, that the methodology of providing
102331 - context and alignment with requirements and prior events and
102332 - commitments is helpful to the District, and should be continued
102333 - for the duration of the Oakland project to assist in resolving
102334 - disputes.
102335 -
102336 - [On 980520 Max Blodgett reported that District Counsel
102337 - attributed substantial savings to Communication Metrics. see
102338 - ref SDS 59 2405]
102340 - ..
102341 - Communication Metrics was ended OA 961231, although Welch
102342 - performed some pro bono work for a week or so to support
102343 - continuity of in-progress initiatives.
102345 - ..
102346 - The Contractor filed for chapter 11 bankruptcy at about the same
102347 - time. Contractor claims have since escalated to more than $60M.
102348 - District counsel have requested support from Communication Metrics
102349 - for the reasons cited by Jim Stout, who has since retired.
102351 - ..
102352 - Communication Metrics is intended to avoid disputes and
102353 - litigation by using concurrent discovery to accomplish win/win
102354 - results for the Corps of Engineers and for the Contractor, as
102355 - was done on the Navy Sewer Line matter. Such outcomes advance
102356 - our partnering objectives.
102358 - ..
102359 - Of course situations arise, where, for example, a contractor in
102360 - severe financial difficulty may find it useful to present
102361 - unfounded claims in hopes of salvaging its existence. This
102362 - observation makes no reference to the Dutra situation per se.
102364 - ..
102365 - Where litigation cannot be avoided, the record produced by
102366 - Communication Metrics is essentially court-room ready evidence.
102367 - This saves the Corps of Engineers significant legal expense.
102369 - ..
102370 - Currently, the District has two full time lawyers working on
102371 - the Oakland project, and approximately 6 claims management
102372 - staff. We estimate for the project the Communication Metrics
102373 - would, if used, permit reduction of one-half lawyer and 2
102374 - claims management staff. Assuming this savings accrues for a
102375 - year, which seems likely based on current progress, the total
102376 - savings would be;
102377 -
102378 - 2.5 x 40 x 52 x $150 = 780K
102380 - ..
102381 - Saving $780K of direct expense of course is not the big prize. The
102382 - interest of the Corps is to ensure that it avoids having to payout
102383 - more than is equitable to the contractor. We have identified
102384 - above some specific issues claimed by the contractor which appear
102385 - at this time will result in cost avoidance, or savings, of
102386 - approximately $3M attributable directly to Communication Metrics.
102387 - ref SDS 0 3168 and ref SDS 0 2501
102389 - ..
102390 - This savings comes at a cost of $50K. Since the Contractor's
102391 - claims have escalated to over $60M. Communication Metrics should
102392 - realize a much larger savings or cost avoidance, if applied for
102393 - litigation support.
102394 -
102395 - [On 981028 District paid $30M on claims over $60M, which may
102396 - reflect value of Communication Metrics in some degree, as
102397 - reported at ref SDS 61 9152]
102398 -
102399 -
102400 -
102401 -
102402 -
Distribution. . . . See "CONTACTS"