Click here to comment!
1...The error rate should be driven by the ratio of time to prepare and
CONTACTS
SUBJECTS
Cost/Benefit of Better Communications
Cost Benefit - Increase Usefulness, Reduce
Measuring Communication Issues
Money, Improving Earnings
Cost Effective SDS Saves Time
Scenario Complex Communications
Calculate Cost Benefit Level of Effort
Humorous Examples
1410 - ..
1411 - Summary/Objective
1412 -
141201 - Follow up ref SDS 12 4593, ref SDS 11 6940.
141202 -
141203 - The need for a better calculation of project management "overhead" is
141204 - evident from discussion with Morris on 960301, ref SDS 3 4725. This
141205 - is supported by letter from Stanford, ref SDS 13 7301.
141206 -
141207 - The error rate should be driven by the ratio of time to prepare and
141208 - number of subjects, in combination with time invested to create a
141209 - record that has relevant, material information, and further based on
141210 - how quickly the record can be researched. If there are a few subjects
141211 - then preparation time is very effective. As the number of subjects and
141212 - relationships grows, error rate increases because the ratio of limited
141213 - preparation time to subjects decreases. This reduces the chances of
141214 - understanding and increases the chance of overlooking critical
141215 - correlations that require attention during a meeting in order to
141216 - achieve effective coordination and cooperation which is the purpose of
141217 - meeting and teamwork.
141218 -
141219 - [See application to calculate rework cost for USACE, ref SDS 15
141220 - 3822.]
141221 -
141222 - [See application of "time to prepare" in USACE cost savings
141223 - report at ref SDS 16 4820.]
141224 -
141225 - Error rate should be a function of...
141226 - ..
141227 - Number of things to remember from POIMS, ref OF 3 3955
141228 -
141229 - Subjects
141230 - Commitments
141231 - Understanding cause and effect, i.e., complexity
141232 -
141233 - Design of work - Details and Specifications
141234 - Stakeholder Impacts/Interests
141235 - Regulations and Codes
141236 - General/Special Conditions
141237 - Policies
141238 - Procedures
141239 - Cost
141240 - Schedule
141241 - Quality
141242 - Safety
141243 - Environment
141244 -
141245 - [See use in meeting with Kieth at Intel on 970728 ref SDS
141246 - 14 3002.]
141247 -
141248 - Number of people who have to remember, coordination
141249 -
141250 - Degree of coordination, i.e., complexity
141251 - Concentration of things each person must remember
141252 -
141253 - Time to prepare, research record to remember accurately...
141254 -
141255 - Information management methodology, i.e., design of system
141256 -
141257 - Size of record
141258 -
141259 - Time invested to capture and organize record
141260 -
141261 - Number of communications required in order to finalize an act,
141262 -
141263 - Time from a communication to performing actual work
141264 -
141265 -
141266 - ..
141267 - Scenario Complex Communications Re Nails
141268 -
141269 - Simple communication:
141270 -
141271 - Tom tells Bill to use six penny nails. Bill nails the board.
141272 - ..
141273 - Complex communication:
141274 -
141275 - Tom tells John to use six penny nails. John tells Mary to
141276 - advise Frank that six penny nails should be included in the
141277 - purchase order for rough hardware, and that Tom wants a memo
141278 - sent to Region I Superintendents directing that they follow
141279 - specification section 06B(3) for materials, which prescribes
141280 - the details where six penny nails are to be used. Steve tells
141281 - Bill to nail the board using six penny nails, even though the
141282 - detail shows 8 penny nails, because Jim said in the team
141283 - meeting this morning that the Superintendent got orders from
141284 - the "top" to use six penny nails. Bill says this detail is a
141285 - change and so does not apply to specification section 06B(3).
141286 - Steve says there isn't enough time to get a clarification, so
141287 - it is better to follow orders.
141288 -
141289 - This scenario reflects...
141290 -
141291 - Humerous example Haley's Comet used for meeting with LTC
141292 - Thompson at the Corps of Engineers, ref SDS 5 8330.
141293 -
141294 - Congestion, bureauracy confuse communication ref SDS 7
141295 - 5503.
141296 -
141297 - On 960125 "Overhead" expense for Communication Metrics
141298 - ensures correct nails get delivered, per scenario for
141299 - Turner's Asilomar presentation, ref SDS 2 2002.
141300 -
141301 - Scenario of Welch Company on Redcor project illustrating
141302 - Peter Drucker's explanation of crucial role of management
141303 - ref SDS 3 5069.
141304 -
141305 - DNRC example, ref SDS 1 5115.
141306 -
141307 - Original meaing drifts away due to interceding information.
141308 - ref SDS 4 3734
141309 -
141310 - [On 990308 example scenario on plastic cube. ref SDS 17 6399]
141311 -
141312 - [On 990728 risk varies along a sliding scale between need for
141313 - security and communciation. ref SDS 18 6935]
141314 -
141315 -
141316 -
141317 -
141318 -