THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700
rodwelch@pacbell.net


S U M M A R Y


DIARY: November 1, 1996 09:30 AM Friday; Rod Welch

Meeting with Port of Oakland/COE to prepare for meeting with Dutra.

1...Summary/Objective
2...Shoaling Shown by Survey Reflects Annual Maintenance Dredging
3...Ralph Gin asked about the intent of provisions in 00800 para 1,
......02480 para 13
......02480 para 14
4...Port of Oakland Assisted in Formulating Contract Provisions
5...Disclosure of Contingent Quantities for Annual Maintenance Dredging
6...Additional Time Linked to Payment for Additional Yardage
7..."Floating" Completion Date
8...Equitable Adjustment Applies Industry Practice for Competitive Bidding
9...Port of Oakland's Order of Work Objectives
10...DE Directs Communication Manager to "Be a Scribe"


..............
Click here to comment!

CONTACTS 
0201 - Corps of Engineers, SFD                                                                                                                                            O-00000632 0302
020101 - Mr. Herb Cheong,; Project Manager
020102 - Project Management Division
0202 - Corps of Engineers, SFD                                                                                                                                            O-00000632 0101
020201 - LTC. Thompson; District Engineer
0203 - Corps of Engineers, SFD                                                                                                                                            O-00000632 0202
020301 - Mr. Thompson F. Keesling, Architect; Assistant Chief
020302 - Construction Operations Division
0204 - Corps of Engineers, Sausalito                                                                                                                                      O-00000645 0201
020401 - Mr. Leonard SooHoo, P.E.; Chief; Construction Service Branch
0205 - Corps of Engineers, SFD                                                                                                                                            O-00000632 0401
020501 - Mr. Thomas Benero; Chief
0206 - Port of Oakland                                                                                                                                                    O-00000647 0201
020601 - Mr. Rob Andrews; Engineering Project Manager
0207 - Port of Oakland                                                                                                                                                    O-00000647 0202
020701 - Mr. Ralph Gin;

SUBJECTS
Schedule Completion of Project, 961101
Time Extenstion 1 CD/8K CY
Schedule for Construction, 52.236-15
Changes in Quantities More than 15%

0706 -
0706 -    ..
0707 - Summary/Objective
0708 -
070801 - Follow up ref SDS 15 0000, ref SDS 14 0000.
070802 -
070803 - The Port offered ideas and background to prepare for meeting with
070804 - Durta at 1000 on planning completion of the work.  Procedures for the
070805 - Port to communicate through COE to the Contractor were confirmed, per
070806 - understandings reported at the Progress Meeting on 961029 of meeting
070807 - on 961024 between Port and COE.
070809 -  ..
070810 - This record includes discussions among COE and the Port of Oakland
070811 - that occurred during breaks in meeting with Dutra, when Dutra was out
070812 - of the room, ref SDS 16 line 90.
070813 -
070814 -      [See follow up submitting confirmation to Dutra of the meeting
070815 -      with it, ref SDS 17 line 83.]
070816 -
070818 -  ..
0709 -
0710 -
0711 - Discussion
0712 -
071201 - Tom Keesling explained the timeline developed yesterday in the
071202 - planning meeting, that shows key issues to be discussed with Dutra
071203 - this morning concerning remaining quantities to be dredged and the
071204 - time/resources required to perform the work, ref SDS 14 line 264.
071206 -  ..
071207 - A key condition arises from information in a recent survey prepared by
071208 - G B Star under contract to Dutra, and a subsidiary of Gahagen and
071209 - Bryant under contract to COE, showing that from inception, Dutra has
071210 - dredged approximately 3.1M CY, and there are approximately 4M CY yet
071211 - to be dredged, without regard to additional shoaling from the date of
071212 - the survey in October 1996 to the date of completion on 970427.
071213 -
071214 -
071216 -  ..
071217 - Shoaling Shown by Survey Reflects Annual Maintenance Dredging
071218 -
071219 - There was discussion that the difference between 6.2M CY found by the
071220 - predredge survey performed under contract section 02480-13, ref OF 7
071221 - line 1178, and the interim survey recently completed by G.B. Star and
071222 - reported at the Progress Meeting on 961029, ref SDS 12 line 720,
071223 - showing 7.1M CY, is attributed to shoaling.
071225 -  ..
071226 - There was discussion that the difference between the contract bid
071227 - quantities of 5.5M CY issued under amendment 0001, and the original
071228 - advertized bid quantities of 6.6M CY, ref OF 2 line 134 (see Claim
071229 - Team meeting 961003 ref SDS 2 line 95), may have reflected anticipated
071230 - shoaling over the 2.5 year period of the contract.  COE's history of
071231 - maintenance dredging appears to indicate that 300K to 800K of new
071232 - material accumulates annually.
071234 -  ..
071235 - There seemed to be discussion that the Port of Oakland has continued
071236 - to perform maintenance dredging within the project area during the
071237 - contract period, which nominally reduces the impact of shoaling on the
071238 - contract pay quantities.  Definitive quantification relative to
071239 - Dutra's contract scope was not discussed.
071241 -  ..
071242 - Consideration occurred of the contractor being paid at the contract
071243 - unit prices for the 6.2M CY but not for the 7.1M CY shown by the
071244 - recent survey, ref SDS 12 line 745, plus any additional shoaling that
071245 - continues to accumulate day-to-day.  Assuming an approximate 500K CY
071246 - of new shoaling will occur between the date of the recent survey and
071247 - the date of actual contract completion, the contract was examined for
071248 - payment of this additional material.
071249 - ..
071250 - Ralph Gin asked about the intent of provisions in 00800 para 1,
071251 - ref OF 5 3383...
071252 -
071253 -         [See explanation at Progress Meeting of need for traceability
071254 -         to original sources using Communication Metrics, ref SDS 18
071255 -         line 348.]
071256 -
071257 -      52.212-3 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR
071258 -      52.21984)
071260 -       ..
071261 -      The Contractor shall be required to (a) commence work under this
071262 -      contract within three (3) calendar days after the date the
071263 -      Contractor receives the notice to proceed, (b) prosecute the work
071264 -      diligently, and complete the entire work ready for use not later
071265 -      than eight hundred and forty (840) calendar days after the date
071266 -      of receipt by him of Notice To Proceed provided, that should the
071267 -      total quantity of material to be paid actually removed under the
071268 -      contract exceed the limit established in the Special Clause
071269 -      "VARIATIONS IN ESTIMATED OUANTITIES - DREDGING", additional time
071270 -      will be allowed at the rate of one (1) calendar day for each
071271 -      8,000 cubic yards in excess of the established limit. The time
071272 -      stated for completion shall include final cleanup of the
071273 -      premises.
071274 -
071275 - ...and para 18, ref OF 5 line 983,
071276 -      ..
071277 -      VARIATIONS IN ESTIMATED QUANTITIES - DREDGING
071279 -       ..
071280 -      Where the quantity of a pay item in this contract is an estimated
071281 -      quantity and where the actual quantity of material within the
071282 -      required dredging prism varies more than fifteen percent (15%)
071283 -      above or below the stated estimated quantity within the required
071284 -      dredging prism, an equitable adjustment in the contract unit
071285 -      price will be made upon demand of either party. The equitable
071286 -      adjustment will be based upon any increase or decrease in costs
071287 -      due solely to the variations above one- hundred fifteen percent
071288 -      (115%) or below eighty-five percent (85%) of the estimated
071289 -      quantity within the required dredging prism. Any equitable
071290 -      adjustment in the contract unit price will also apply to that
071291 -      part of the actual quantity of allowable overdepth material above
071292 -      one-hundred fifteen percent (115%) or below eighty-five percent
071293 -      (85%) of the estima- ted quantity.
071294 -
071295 - ...and section 02480 para 13 and 14 dealing with surveys, measurement
071296 - and payment, including shoaling.
071298 -       ..
071299 -      02480 para 13
071300 -
071301 -      The Contractor will perform a predredge survey prior to
071302 -      commencement of dredging for the entire project and postdredge
071303 -      surveys upon completion of each polygon for acceptance or as
071304 -      otherwise approved by the Contracting Officer. After the
071305 -      completion of all dredging work, the Contractor shall perform a
071306 -      final postdredge survey for the entire work to determine if any
071307 -      shoaling has occured after the polygons were accepted as approved
071308 -      by the Contracting Officer. All polygons found to be in
071309 -      compliance with the contract requirements will be accepted
071310 -      finally and be measured for payment as stated in Paragraph
071311 -      "MEASUREMENT AND PAYMENT", subparagraph "Measurement for Payment"
071312 -      hereinbelow. If the postdredge surveys data indicates that the
071313 -      project is not to the depth required in some or all of the
071314 -      polygons, then the Contractor shall resume dredging within seven
071315 -      calendar days after completion-of the field survey work to
071316 -      complete the work down to project depth. The Contractor shall
071317 -      perform additional surveys as required until the work is complete
071318 -      at no additional cost to the Government. When the polygons are
071319 -      found to be in satisfactory condition, they will be accepted.
071321 -       ..
071322 -      02480 para 14
071323 -
071324 -      14.1     Measurement for Payment. Measurement for payment of the
071325 -      total amount of material dredged will be made based on the cubic
071326 -      yards of material in-place, by computing the volume between the
071327 -      bottom surface shown by soundings of the Contractor's survey
071328 -      taken before dredging and the bottom surface shown by soundings
071329 -      of the final survey compared with the neat line template, using
071330 -      the average-end-area method. This quantity shall include
071331 -      excavation performed within the allowable overdepth limits and
071332 -      exclude excessive dredging as specified under paragraph
071333 -      "OVERDEPTH AND EXCESSIVE DREDGING".
071335 -       ..
071336 -      14.2     The contract drawings represent conditions existing on
071337 -      the date of the survey shown on the drawings and are for
071338 -      information purposes only. The pre-dredge survey performed by the
071339 -      Contractor will be used in determining quantity of material for
071340 -      payment. Determination of quantities removed and the deductions
071341 -      made therefrom to determine quantities by in-place measurement to
071342 -      be paid in the area specified after having once been made will
071343 -      not be reopened, except on evidence of collusion, fraud or
071344 -      obvious error. No payments will be made until all computations,
071345 -      field notes and drawings are received for progress payment.
071346 -
071347 -      .
071348 -      .
071349 -      .
071350 -      ..
071351 -      These prices and payments shall constitute full
071352 -      compensation for predredge and postdredge surveys, progress
071353 -      payment surveys, quality control surveys, barge filling area
071354 -      surveys, dredging and disposing of all materials including
071355 -      required and allowable overdepth, all in accordance with the
071356 -      drawings and specifications.
071358 -       ..
071359 -      14.4     Shoaling. Shoaling occurring within the project limits
071360 -      after acceptance of any polygon and prior to the completion of
071361 -      the contract shall be removed if directed by the Contracting
071362 -      Officer. Such work will be subject to the "CHANGES" clause.
071363 - ..
071364 - There was discussion that these provisions may require the
071365 - Contractor to remove at no additional cost to the government material
071366 - that shoals into the work area between the date of the predredge
071367 - survey, and the date of the acceptance survey, which in some cases is
071368 - 2 years later, and that time extensions are predicated on increases of
071369 - 15% above a bid item amount use the predredge survey as a baseline.
071370 -
071371 -      [See where this opinion was conveyed to the Contractor, ref SDS
071372 -      16 line 320.]
071374 -       ..
071375 -      [See meeting with Port re its 961122 memo and meeting with
071376 -      Contractor on 961126, ref SDS 19 line 87.]
071378 -  ..
071379 - Port of Oakland Assisted in Formulating Contract Provisions
071380 -
071381 - Rob Andrews noted that he contributed to preparing COE contract
071382 - requirements in either or both sections 02480 para 13 and 14.  There
071383 - was discussion that Chris Shields is reviewing these provisions, ref
071384 - SDS 8 line 167.  Rob recalled that Chris was not involved in the
071385 - original formulation of the provisions, and the underlying objectives
071386 - and implementation intended.  There seemed to be information developed
071387 - that COE engineers who prepared these provisions have left the
071388 - organization, except possibly Ken Khun.
071389 -
071390 -
071392 -  ..
071393 - Disclosure of Contingent Quantities for Annual Maintenance Dredging
071394 -
071395 - Assuming the intent was for the Contractor to include an allowance to
071396 - dredge annual shoaling material which is typically performed under a
071397 - contract for Maintenance Dredging, then what basis was the bidder to
071398 - determine the quantity?  One basis would be the historical record of
071399 - annual maintenance dredging.  What other process or method could the
071400 - contractor use to calculate the outlay to perform 2M additional yards
071401 - for a 2.5 year period?
071402 -
071403 -     [See COE team analysis, ref SDS 14 line 272.]
071405 -  ..
071406 - Was it intended to perform annual Maintenance Dredging under the
071407 - contract to deepen the Oakland Harbor to -42' MLLW, and not state this
071408 - to bidders, but rather require them to include the cost of dredging 2M
071409 - additional cubic yards for the price of dredging 5.5M CY?
071410 - ..
071411 - Was it intended for bidders to determine independently there
071412 - would be 36% more material to dredge than requested by the bid
071413 - documents?
071415 -  ..
071416 - If the 5.5M CY value reflects a decision to remove annual shoaling
071417 - from the pay quantities, since it may have been seen to more properly
071418 - belong to the budget for annual maintenance dredging, and if the
071419 - shoaling today is actually 500K CY greater than the 6.6M original pay
071420 - quantity, what basis were bidders to have calculated the actual amount
071421 - of shoaling to include in their bids?
071423 -  ..
071424 - COE's superior knowledge of the information required to calculate
071425 - shoaling may warrant consideration with respect to determining the
071426 - proper accounting for this part of the work.  Timely analysis of this
071427 - matter may improve chances of minimizing ultimate cost to the
071428 - government.
071429 -
071430 -
071432 -  ..
071433 - Additional Time Linked to Payment for Additional Yardage
071434 -
071435 - Rob Andrews drew attention to the provisions in section 00800 para 1,
071436 - FAR 52.212-3, which states:
071437 -
071438 -       The Contractor shall be required to (a) commence work under this
071439 -       contract within three (3) calendar days after the date the
071440 -       Contractor receives the notice to proceed, (b) prosecute the
071441 -       work diligently, and complete the entire work ready for use not
071442 -       later than eight hundred and forty (840) calendar days after the
071443 -       date of receipt by him of Notice To Proceed provided, that
071444 -       should the total quantity of material to be paid actually
071445 -       removed under the contract exceed the limit established in the
071446 -       Special Clause "VARIATIONS IN ESTIMATED OUANTITIES - DREDGING",
071447 -       additional time will be allowed at the rate of one (1) calendar
071448 -       day for each 8,000 cubic yards in excess of the established
071449 -       limit. The time stated for completion shall include final
071450 -       cleanup of the premises.
071451 - ..
071452 - Section 00800 para 18 states at ref OF 5 line 983:
071453 -
071454 -       Where the quantity of a pay item in this contract is an
071455 -       estimated quantity and where the actual quantity of material
071456 -       within the required dredging prism varies more than fifteen
071457 -       percent (15%) above or below the stated estimated quantity
071458 -       within the required dredging prism, an equitable adjustment in
071459 -       the contract unit price will be made upon demand of either
071460 -       party. The equitable adjustment will be based upon any increase
071461 -       or decrease in costs due solely to the variations above one-
071462 -       hundred fifteen percent (115%) or below eighty-five percent
071463 -       (85%) of the estimated quantity within the required dredging
071464 -       prism. Any equitable adjustment in the contract unit price will
071465 -       also apply to that part of the actual quantity of allowable
071466 -       overdepth material above one-hundred fifteen percent (115%) or
071467 -       below eighty-five percent (85%) of the estima- ted quantity.
071468 - ..
071469 - There seemed to be discussion that these provisions taken
071470 - together could be construed to mean the contractor is awarded
071471 - additional time to complete the work for the purposes of assessing
071472 - liquidated damages, based on whether the quantity dredged for a
071473 - particular bid item exceeds the limit of 15% set out in section 00800
071474 - para 18.
071476 -  ..
071477 - There was also discussion that the figures to be used for making this
071478 - calculation are the original bid quantity and the predredge survey,
071479 - which was also considered yesterday by the COE Claim Team, ref SDS 14
071480 - line 279.
071482 -  ..
071483 - Analysis was offered that since it appears that there are no bid items
071484 - for which the difference between the original pay quantity and the
071485 - predredge survey exceeds 15%, an interpretation could be that the
071486 - contractor is obligated to dredge an additional 2M CY with no
071487 - additonal time, and is to dredge approximately 7.6M CY for the price
071488 - of dredging 6.2M CY.  These ideas were considered yesterday by the COE
071489 - Claim Team, ref SDS 14 line 278.
071490 -
071491 -      [See work on spreadsheet to analyse quantities, ref SDS 20 line
071492 -      69, and COE Project Team meeting on Cure Notice, ref SDS 21 line
071493 -      125.]
071494 -
071496 -  ..
071497 - "Floating" Completion Date
071498 - --------------------------
071499 - Discussion indicated that the contract provisions result in an
071500 - inherent indefinite completion date, that can only be determined based
071501 - on a complex formula using the the final pay quantities and
071502 - interpretation of several different contract provisions.
071504 -  ..
071505 - Tom Benero discussed the advantages of conveying in a clear and direct
071506 - manner the completion date subject to liquidated damages, so that the
071507 - contractor can plan performance of the work.
071508 -
071509 -
071511 -  ..
071512 - Equitable Adjustment Applies Industry Practice for Competitive Bidding
071513 -
071514 - There was strong concensus to research the contract and objectives to
071515 - ensure an equitable adjustment results for the Contractor and the
071516 - Government.
071517 -
071518 - DE set the government's position as requiring the contractor to submit
071519 - a practical schedule for completing the work to be performed so that
071520 - determinations can be made with respect to entitlement to additional
071521 - time, adjustments in payment, if any, and coordinating acivities of
071522 - those using the facilities being improved under this contract, all as
071523 - required by the schedule provisions cited in COE's letter to the
071524 - Contractor dated 961028, ref DIP 1 line 33.
071525 -
071526 -
071528 -  ..
071529 - Port of Oakland's Order of Work Objectives
071530 -
071531 - Tom Keesling asked if the Port of Oakland management has any
071532 - preferences for performing the work with respect to sequence, per ref
071533 - SDS 14 line 268.
071534 -
071535 - Ralph Gin reported on inquiries by representatives of Dutra Dredging
071536 - which were outside the contract line of communication of COE.  He
071537 - indicated Dutra gave indicatiions to the Port that it would follow a
071538 - sequence preferred by the Port if Dutra were paid additional funds.
071540 -  ..
071541 - Herb Cheong advised that COE does not intend to direct the Contractor
071542 - on its order of work except within the meaning of the contract
071543 - requirement for the Contractor to submit a "practicable" schedule.
071544 - ..
071545 - Rob Andrews advised it would be practicable for the Port to have
071546 - the work accepted on the basis of a location containing a berth and a
071547 - channel route to the ocean, such that a portion of the completed work
071548 - provides useable contigous routes in the harbor.
071550 -  ..
071551 - There were no other preferences offered that reflect the Port of
071552 - Oakland's needs and objectives.
071553 -
071554 -
071555 -
071556 -
0716 -

SUBJECTS
Scribe, Takes Notes, Does Not Speak
Welch Prepare Notes of Weekly Progress
Speaking at Meetings
Fear Communication Manager Replaces
Facilitate Meetings, Use SDS Record
70% of Day Wasted in Meetings, Only 10% of
Conversation Discursive, Speculative
Listening & Dialog Inadequate, Need

2210 -
221101 -  ..
221102 - DE Directs Communication Manager to "Be a Scribe"
221103 -
221104 - The meeting today became a dynamic exchange of views on the meaning of
221105 - contract provisions.
221106 -
221107 - I asked a few questions to clarify the meaning of discursive dialog
221108 - that entailed half-sentences, nods and unspecified references to the
221109 - contract and the job record.  I also offered some correlations with
221110 - the record to facilitate the meeting.
221111 -
221112 -     [See meeting on 961213, ref SDS 23 line 125, and later discovery
221113 -     of need for notes of the meeting, ref SDS 25 line 1017.]
221115 -  ..
221116 - At one point, DE seemed to indicate that these questions were
221117 - inappropriate by looking at me and saying:
221118 -
221119 -                        "Be a Scribe."
221120 -
221121 -     ...which seems to reflect the Commander's understanding of the
221122 -     Communication Manager role, as related by Tom Benero at ref SDS 7
221123 -     line 300.  It likely came from the meeting with Max at ref SDS 1
221124 -     line 111.
221126 -      ..
221127 -     [See follow up where DE affirmed that the "Scribe" does not speak,
221128 -     ref SDS 22 line 118; and, later cancellation of Communication
221129 -     Metrics, ref SDS 24 line 98.]
221130 - ..
221131 - Thereafter I asked no further questions.  Following the event, I
221132 - asked several speakers for clarifications and they provided
221133 - information on some matters and were unable to recall what they had in
221134 - mind on other matters.
221136 -  ..
221137 - During the meeting with Dutra, I passed notes to Tom Benero to support
221138 - his representations and ensure they covered the complete agenda.
221139 - During Tom Keesling's presentation of quantity and job schedule, I
221140 - passed a note to Tom Benero to suggest a break, which lead to much of
221141 - the above exchange outside the presence of Dutra.
221142 -
221143 -
2212 -
Distribution. . . . See "CONTACTS"