1...COE will investigate and advise of any additional information needed
2...Bob Johnston suggested that Phil submit details for the record on when
CONTACTS
0201 - Dutra Oakland Project Ofc O-00000648 0201
020101 - Mr. Chris Peterson;
020102 - Mr. Phil Torres;
020103 - Mr. Ken Esse; Safety Engineer
020104 - Mr. Steve Hutchison;
020105 - Mr. Jack Fink;
0202 - Dutra Dredging Company
020201 - Mr. Bill Dutra; Chairman;
020202 - Mr. Robert D. Johnston; President O-00000644 0101
020203 - Mr. James J. Galli, P.E.; Manager
020204 - West Coast Dredging
0203 - Corps of Engineers, SFD
020301 - Mr. Herb Cheong,; Project Manager
020302 - Mr. Thomas Benero; Chief
020303 - Ms. Monteze Jaggers; Procurement Analyst
020304 - Mr. Marcus Tikotsky; Contract Specialist
0204 - Corps of Engineers, SFD
020401 - Mr. Glen N. Chafe 415 331 0404 O-00000646 0102
020402 - Mr. Thomas W. White; Project Engineer
0205 - Port of Oakland O-00000647 0201
020501 - Mr. Ralph Gin;
020502 - Mr. Jack Aydelott;
020503 - Mr. Rob Andrews; Engineering Project Manager
0206 - Gahagan & Bryant Associates, Inc. O-00000651 0102
020601 - Mr. Rick Olejniczak; Vice President
0207 - Gahagan & Bryant Associates, Inc. O-00000651 0201
020701 - Mr. Rob Greybill;
SUBJECTS
Corps of Engineers, SFD, Oakland Project
Weekly Progress Meeting, 961022
0404 -
0404 - ..
0405 - Summary/Objective
0406 -
040601 - Follow up ref SDS 4 0000, ref SDS 3 0000.
040602 -
040603 - The barge Antone is being serviced, Paula Lee is working in the
040604 - Turning Basin. DB 24 has been taken off the project. COE needs agenda
040605 - from Dutra to schedule Partnering meeting. Contractor updating its
040606 - schedule. Contractor requests more time to submit proposed scope for
040607 - debris removal based on new information from Port of Oakland.
040608 - Contractor was informed it must substantiate its proposals for extra
040609 - payment relative to its original bid.
040611 - ..
040612 - COE is arranging to remove obstacles from contractor's work area.
040613 - Survey nearly complete. Contractor reports cash flow problems
040614 - impacting payment of pending survey. Contractor was informed funds
040615 - being withheld due to slow progress will be reviewed for release upon
040616 - a showing that production improves to recoup delayed progress. Time
040617 - extensions will be reviewed based on pending survey results relative
040618 - to original bid quantities.
040619 -
040620 - [See submission for distribution at ref SDS 10 line 53.]
040621 -
040622 -
0407 -
SUBJECTS
Commencement, Prosecution, Completion of Work
Galbraith, Disposal
0804 -
080501 - ..
080502 - Project Status - Production Slowed by Debris in Work Areas
080503 -
080504 -
080505 - [See correction on slowed production not caused by debris in work
080506 - area, ref SDS 12 line 150.]
080507 -
080508 - a. The weekly report on "Hard Digging" for the period ending
080509 - 961022, was not distributed/discussed, pending receipt from
080510 - Dutra of QC reports for period 961017 - 961021, ref DIT 1 line
080511 - 29.
080513 - ..
080514 - Antone being prepared past 2 days for christening ceremony
080515 - tomorrow, 961023.
080517 - ..
080518 - b. Contractor did not report completion status in Turning Basin
080519 - (e.g., 20%, 50%, 90% complete??). Dutra indicated it is still
080520 - working on an updated schedule.
080522 - ..
080523 - c. Contractor advised it wishes to submit tomorrow a new work
080524 - operation for consideration of an RFP to perform piling/debris
080525 - removal in Todd Wing and Schnitzer Wings.
080527 - ..
080528 - d. Dutra will submit issues for partnering meeting so a meeting
080529 - can be scheduled based on level of effort and duration of event
080530 - required by issues.
080531 -
080532 -
080533 -
080534 -
0806 -
SUBJECTS
Communication Metrics
SDS Notes for Weekly Progress Meetings
1004 -
100501 - ..
100502 - Dutra Reports Improved use of Communication Metrics
100503 -
100504 - Bob Johnston indicated the notes of the meeting for 961015 are better
100505 - than those for the meeting on 961009, as discussed at the meeting on
100506 - 961015. ref SDS 4 1217
100507 -
100508 - Bob recalled that Tom White's "minutes" for earlier meetings were
100509 - helpful to Dutra.
100511 - ..
100512 - Tom Benero reviewed the objective of using Communication Metrics to
100513 - reach timely, accurate decisions in performing the work, as set out in
100514 - the notes for the meeting on 961001, ref SDS 2 6654. Rod Welch
100515 - explained this is accomplished by aligning understandings from
100516 - meetings, calls and documents (i.e., all management information) with
100517 - contract requirements. Timely input on misunderstandings avoids
100518 - mistakes that cost money and delay the work, per the notes for the
100519 - meeting on 961015, ref SDS 4 1217.
100520 -
100521 -
100522 -
100523 -
100524 -
1006 -
SUBJECTS
Partnering, COE, Port, Dutra
Dredging, Shoaling
Surveys Predredge, Postdredge
1305 -
130601 - ..
130602 - Partnering Meeting - Dutra/COE will Submit List of Issues
130603 -
130604 - Leonard asked if Dutra has submitted its list of issues to be
130605 - discussed at a partnering meeting.
130606 -
130607 - Bob Johnston recalled indicating Dutra was trying to submit its list
130608 - by last Friday, per ref SDS 4 line 221. He noted this morning that
130609 - scheduling a date for the meeting is important. Dutra is concerned
130610 - about new people at COE.
130612 - ..
130613 - Leonard SooHoo advised he has a call in to the firm that facilitates
130614 - these meetings. He asked if Dutra is agreeable to using the same
130615 - location used for the last partnering meeting? There seemed to be
130616 - agreement on this point.
130618 - ..
130619 - There was discussion that the duration of the meeting is based on the
130620 - number and complexity of issues. Tom White recalled that the last
130621 - partnering meeting could have benefited from a second day. There
130622 - seemed to be agreement on scheduling two days.
130624 - ..
130625 - Leonard noted that scheduling the meeting requires informing the
130626 - facilitators of what is to be "partnered." Once the agenda is
130627 - received from Dutra, COE can schedule the meeting and issue a
130628 - modification to the contract.
130629 -
130630 - [See follow up deferring partnering meeting ref SDS 12 line 363.]
130631 -
130632 -
1307 -
SUBJECTS
Service Dredging Equipment
Paula Lee, Turning Basin
Antone, Production Rates - 17 CY Bucket
1905 -
190601 - ..
190602 - Antone Being Serviced
190603 -
190604 - Jim Galli advised that the Antone is being serviced to prepare it for
190605 - the christening ceremony to be held tomorrow at 1230. It is expected
190606 - back in production following the ceremony tomorrow.
190607 -
190608 - The Paula Lee is working in the Turning Basin.
190610 - ..
190611 - The DB 24 is off the job.
190612 -
190613 -
190615 - ..
190616 - Change from 17 to 24 CY Bucket on Antone
190617 -
190618 - Dutra confirmed it expects to install the 24 CY bucket on the Antone
190619 - following the christening ceremony on 961023, per understandings from
190620 - the 961009 meeting, ref SDS 3 line 167.
190621 -
190622 -
190623 -
190624 -
1907 -
SUBJECTS
Schedule for Construction, 52.236-15
Commencement, Prosecution, Completion of Work
Extension of Time, 1 CD/8K CY
Plan of Operation
2406 -
240701 - ..
240702 - Dutra to Submit Updated Schedule
240703 -
240704 - There was discussion of Dutra's work sequence being impacted by a
240705 - variety of factors, e.g., obstacles that need to be moved from work
240706 - area, debris removal.
240707 -
240708 - Contract section 02480 4.2 calls for the contractor to submit a weekly
240709 - plan of operation for dredging that covers these issues. Dutra's plan
240710 - for the current week was not offered for review at the meeting today.
240712 - ..
240713 - Marcus Tikotsky asked about Dutra's submission of an updated Schedule,
240714 - discussed at the meeting on 961015, ref SDS 4 5883.
240716 - ..
240717 - Bob Johnston indicated Dutra is still working on updating its project
240718 - Schedule. This Schedule can show Dutra's sequence of work and
240719 - opportunities for "work arounds" to avoid delays and maintain
240720 - production. There seemed to be considerable expertise at the meeting
240721 - today on accomplishing this goal, which in turn, permits planning by
240722 - the Port of Oakland and others in utilizing harbor facilities and
240723 - access ways.
240724 -
240725 - [See receipt of schedule on 961112, ref SDS 15 0000.]
240727 - ..
240728 - Tom Benero advised that COE understanding from Dutra's progress
240729 - indicates it cannot complete the work by April 1997.
240731 - ..
240732 - There was discussion of Dutra having encountered additional material.
240734 - ..
240735 - Tom Benero noted the contract permits Dutra an additional day to
240736 - complete the work for each 8K CY above the original bid quantities.
240738 - ..
240739 - Assessment can be made by COE with respect to this matter using survey
240740 - results, upon notification by Dutra that it needs additional time
240741 - based on a properly supported updated schedule.
240742 -
240743 - [See subsequent analysis by Port of Oakland and COE ref SDS 13
240744 - line 137, and discussion with the Contractor, ref SDS 14 line
240745 - 305.
240746 -
240747 -
2408 -
SUBJECTS
Payments under Fixed Priced Construction
2503 -
250401 - ..
250402 - COE Responsible to Manage Payment Based on Record of Performance
250403 -
250404 - Bill Dutra asked what steps Dutra can take to obtain release of
250405 - retained earnings?
250406 -
250407 - Tom Benero advised COE is retaining earnings because Dutra's
250408 - production rate shows it cannot meet the contract completion date.
250409 - Production reports indicate Dutra has not averaged 10K per day as
250410 - expected when the Antone was mobilized at the site.
250412 - ..
250413 - Rob Andrews offered that in order to achieve the original expected
250414 - average production of 10K CY/Day, Dutra must begin averaging 14K to
250415 - 15K CY per day.
250417 - ..
250418 - Tom Benero indicated COE would consider releasing retained earnings
250419 - and cease withholding future earnings, if Dutra can begin averaging
250420 - 14K CY per day, and/or take such other measures that will reasonably
250421 - result in completing the work within the contract period, as adjusted
250422 - for any additional yardage relative to original bid quantities.
250423 -
250424 - [See follow up to improve management so production can improve,
250425 - ref SDS 11 line 82.]
250427 - ..
250428 - [See reports of reduced production at ref SDS 12 line 129, and COE
250429 - initiative on updating schedule, ref SDS 12 line 337.]
250430 -
250431 -
250432 -
2505 -
SUBJECTS
Inner Harbor Work Area, Schnitzer
Piling encountered, Schnitzer
Todd Turning Basin
Obstructions in Todd Wing (Dolphin, Ship,
Debris Removal
0019 Remove concentrated debris Todd and
3108 -
310901 - ..
310902 - Piling/Debris - Dutra Submitting Revised Work Operation
310903 -
310904 - Tom Benero advised COE has investigated Dutra's report in its 961007
310905 - letter, ref DRP 1 line 26, and is prepared to issue an RFP based upon
310906 - input from Dutra in the meeting on 961017, ref SDS 6 line 89, per
310907 - understandings at the Progress Meeting on 961015, ref SDS 4 line 418.
310909 - ..
310910 - COE is considering a directive for Dutra to remove debris in excess of
310911 - the requirements of para 02480 para 9, in the Todd and Schnitzer Wings
310912 - based on assuming approximately a 1' - 2' depth of debris throughout
310913 - these areas. It is recognized that debris will not occur throughout
310914 - the areas, however, the actual condition can only be determined by
310915 - performance of the work, since all of the work to be performed is
310916 - underwater. Dutra holds it is "critical" for it to commence work in
310917 - these areas, and so for budgeting purposes this calculation can be
310918 - determined, as discussed with Dutra at the 961017 meeting, ref SDS 6
310919 - line 134. Actual payment will be based on actual yardage of debris
310920 - removed based on visual observation and measurement by COE during the
310921 - work, subject to reasonable challenge by Dutra.
310923 - ..
310924 - Based on discussions with Dutra, COE expects the work operation may
310925 - consist of a dredge, dredging scows and other equipment, such as flat
310926 - barges, as Dutra determines is needed to load piling and other debris
310927 - found to be in excess of the requirements of para 02480 para 9, ref
310928 - SDS 6 line 210. Since the extent and location of debris is unknown,
310929 - using dredging scows for material suitable for disposal at Galbraith,
310930 - will enable Dutra to maintain consistent use of the dredge without
310931 - concern about encountering material suitable for disposal at
310932 - Galbraith, and/or commingling it with debris to be paid at a price
310933 - under this RFP significantly higher than the contract price for
310934 - dredging, due to increased handling and possibly reduced production
310935 - rate relative to that for dredging contract pay item work.
310937 - ..
310938 - To the extent Dutra estimates its production on dredging suitable
310939 - material under this RFP will be impacted, it can include the cost for
310940 - this impact in the cost for removing debris.
310942 - ..
310943 - Therefore, COE expects to request Dutra's pricing for the following
310944 - new pay item:
310945 -
310946 -
310947 - Remove debris in Todd and Schnitzer Wings Tons
310948 - above requirements of 02480 para 9 ----
310949 -
310951 - ..
310952 - At the meeting on 961017 Dutra raised a variety of options and
310953 - complexities in disposing of the debris and disposing of suitable
310954 - material at Galbraith, including separating material. Under this
310955 - proposed RFP, Dutra can determine the most economical solution,
310956 - subject to review by COE for reasonableness.
310958 - ..
310959 - Ideas considered on reasonableness were then discussed, as follows...
310960 -
310961 -
310963 - ..
310964 - COE Recognizes Advantages of Separating Debris at Galbraith
310965 -
310966 - Glen Chafey reported investigation indicating separation can be
310967 - performed at the Liberty Off-loader with specialized equipment in
310968 - order to minimize duplicate handling and hauling material to
310969 - Galbraith.
310971 - ..
310972 - Bill Dutra observed the logic of this approach is sound to a point.
310974 - ..
310975 - There was discussion about San Franciscan sand cannot pass through
310976 - grates. Creosote piles may penetrate into clay. Sorting debris
310977 - presents a challenge.
310978 -
310980 - ..
310981 - Changed Material Encountered - "Gumbo"
310982 - New Information Indicates Revised Dutra Work Operation
310983 -
310984 - Bill Dutra advised of progress Dutra has made identifying the possible
310985 - scope of debris removal based on new information from the Port of
310986 - Oakland, per discussion with Rob Andrews at the meeting on 961015....
310987 - ref SDS 4 line 366.
310989 - ..
310990 - Bill feels identifying scope is 95% complete. He indicated this
310991 - warrants using a cheaper piece of equipment, and disposing of the
310992 - debris in the Redwood Land Fill. It was unclear if disposal could be
310993 - accomplished by barge, or by truck, as discussed at the 961017
310994 - meeting. If debris is disposed by barge, then payment can be by CY
310995 - instead of by ton, which seems to be more applicable to a trucking
310996 - operation. COE is agreeable to using cheaper, and more effective
310997 - equipment, however, it is Dutra's responsibility to select an
310998 - economical mix of resources for the work under all of the
310999 - circumstances involved.
311000 - ..
311001 - Bill cited the potential for the debris to contain a wide
311002 - variety of elements including wood, concrete, steel piles.
311004 - ..
311005 - Bob Johnston called this mixture "gumbo."
311007 - ..
311008 - Such potential is consistent with the original understanding that,
311009 - having encountered complex materials, i.e., "gumbo," it is not
311010 - possible to formulate a work operation predicated on encountering a
311011 - single type of debris within finite contiguous regions, other than by
311012 - making general assumptions based on data from the Port of Oakland
311013 - archives reviewed this morning, that show evidence of prior structures
311014 - where none are presently observable from above water. Whether this
311015 - site was used previously as a dump, formal or otherwise at different
311016 - times over the past 100 years and thus presents a layered environment
311017 - of debris and mud, is unknown, but possible based on the material
311018 - removed to date.
311019 -
311020 - [See follow up on spec requirements. ref SDS 8 4933]
311022 - ..
311023 - A variety of disposal scenarios were considered in addition to those
311024 - identified by Glen.
311026 - ..
311027 - Bill proposed setting up a separate debris removal operation,
311028 - consistent with COE intent under the above pay item being considered
311029 - by COE.
311030 -
311031 -
311033 - ..
311034 - Avoiding Commingling Contract Dredging with Debris Removal
311035 -
311036 - There was discussion that using dredging scows for contract dredge
311037 - material in conjunction with the debris removal operation, will enable
311038 - the contractor's dredge to continually work, rather than having to
311039 - place suitable material in the debris barge, or alternatively drop it
311040 - back in the water and then dredge it again, in the event a bucket load
311041 - of suitable material is encountered.
311043 - ..
311044 - Indeed it seems likely that the depth of debris will vary across the
311045 - work area, so that at some locations there will necessarily be greater
311046 - concentrations of debris than at other locations in the target work
311047 - areas. Having the two scows available at all times enables the work
311048 - to proceed at full force under all contingencies.
311050 - ..
311051 - Bob Johnston indicated there may be aspects of the work which make
311052 - this method less economical than using a single barge for debris
311053 - removal until that operation is determined to be completed, then
311054 - commencing contract dredging.
311055 - ..
311056 - Contract section 02480 para 9 requires the contractor to perform
311057 - debris removal as part of the price for contract dredging, so Dutra
311058 - should submit its explanation of distinguishing this operation from
311059 - the requirements of this contract provision.
311061 - ..
311062 - Dutra requested another day to analyze the new information provided by
311063 - the Port and to formulate its approach. Dutra will submit its views
311064 - to COE tomorrow, 961023, and thereafter COE will issue an RFP.
311065 -
311066 - [See receipt of information from Dutra a week later, ref SDS 12
311067 - line 462.]
311068 -
311069 -
3111 -
SUBJECTS
Inner Harbor Work Area, Schnitzer
Todd Turning Basin
Obstructions in Todd Wing (Dolphin, Ship,
3405 -
340601 - ..
340602 - Obstructions Impair Access to Work in Todd Wing; COE Investigating
340603 -
340604 - Dutra urged prompt action on removing obstacles in its work area so
340605 - dredging can commence.
340606 -
340607 - At this time COE understands from Dutra's reports that such obstacles
340608 - are in the Todd and Schnitzer Wings which are pending formulation of a
340609 - solution for debris removal.
340611 - ..
340612 - Rob Andrews indicated the Port of Oakland cannot take action because
340613 - the area in question is under Federal jurisdiction.
340615 - ..
340616 - Leonard SooHoo reported COE counsel contacts with a judge to take
340617 - necessary action. These efforts will be pursued to expedite the work.
340619 - ..
340620 - There was discussion that there are several classes of such obstacles:
340621 -
340622 - 1. The floating dock has a long history of a presence at its
340623 - location which may result in delayed relocation. Options to
340624 - accommodate this delay include delaying work in this region;
340625 - removing it from the contract to be performed by others.
340626 -
340627 - [See report by Dutra that this may not be a problem, ref
340628 - SDS 12 line 399.]
340630 - ..
340631 - 2. Last week one ship was reported in the way, today Dutra
340632 - reported another ship is now in the way, though possibly in
340633 - the process of being moved.
340635 - ..
340636 - This is a dynamic condition which requires coordination with
340637 - authorities to place the contractor's work area off limits for
340638 - berthing ships during the period when work is being performed.
340640 - ..
340641 - There was discussion about coordinating with ship owners and
340642 - those who direct where ships are berthed, to simply avoid
340643 - conflicts with Dutra operations. The practicalities and level
340644 - of effort for accomplishing such coordination were not fully
340645 - explored at the meeting today.
340646 -
340647 - [See report by Dutra that this problem is limited mainly
340648 - to Pembina, ref SDS 12 line 402.]
340650 - ..
340651 - 3. Physical structures not shown on the drawings, such as a
340652 - concrete dolphin.
340654 - ..
340655 - These items need to be identified and reported in a drawing
340656 - for investigation by COE.
340658 - ..
340659 - Steve Hutchison said Dutra can prepare a sketch showing the
340660 - location of such items relative to the Dutra work areas.
340662 - ..
340663 - COE can then investigate and arrange with Dutra or others to
340664 - address this issue.
340665 -
340666 - [See report by Dutra of submitting sketch, ref SDS 12 line
340667 - 493.]
340668 -
340669 -
340670 -
3407 -
SUBJECTS
Safety and Health, Access/Egress of Workers
3503 -
350401 - ..
350402 - Inspectors Need Ferry Terminal Access after 1030p
350403 -
350404 - There was no discussion of progress on this issue, nor indication
350405 - that it is of continuing concern to the project.
350406 -
350407 -
350408 -
3505 -
SUBJECTS
Safety and Health, Safety Seminar
Safety Improvements
Safety Meeting on Current Accidents/Incidents
Emergency Numbers
3906 -
390701 - ..
390702 - New Procedures to be Posted from Dutra Safety Event
390703 -
390704 - Bob Johnston asked Ken Esse about progress coordinating with Al
390705 - Bennitt on the memo from Dutra's safety event on 960923, per meeting
390706 - on 961001, ref SDS 2 line 281, and on 961009, ref SDS 3 line 356.
390707 -
390708 - Ken said he will contact Al to finalize this memo.
390709 -
390710 - [Dutra submitted a report at 961112 meeting, ref SDS 16 line
390711 - 807.]
390713 - ..
390714 - A determination can then be made on changes that might be indicated to
390715 - the project safety program.
390716 -
390717 -
390719 - ..
390720 - Safety Meeting Held For All Dutra Crews on 961010
390721 -
390722 - There was no discussion during the meeting of Dutra's response to
390723 - Leonard SooHoo's request for results on safety meeting held on 961010,
390724 - per meeting on 961009, ref SDS 3 line 364, and whether any new
390725 - procedures to improve safety have been promulgated as a result of
390726 - recent experience, cited in the meeting on 961009, and reported to be
390727 - of major concern to COE District Commander at the 960924 meeting, ref
390728 - DIP 1 line 21.
390729 -
390730 -
390732 - ..
390733 - Emergency Phone Numbers Will Be Posted
390734 -
390735 - Ken Esse advised adequate Emergency phone numbers are posted at Dutra
390736 - work locations, including floating equipment. Dutra indicates COE has
390737 - a list of emergency numbers in order for timely responsiveness.
390738 -
390739 - COE will investigate and advise of any additional information needed
390740 - on this matter.
390741 -
390742 -
390743 -
3908 -
SUBJECTS
Commencement, Prosecution, Completion of
Navy Sewer Line, RR Slope Stability
Sewer Line Installation
COE Directs Contractor to Proceed
4306 -
430701 - ..
430702 - Navy Sewer Line - Dutra Has Not Secured UPRR Permit
430703 -
430704 - Bob Johnston advised that the Union Pacific Railroad has returned
430705 - Dutra's check for obtaining a permit to perform the crossing of the
430706 - UPRR railroad line as shown in the contract plans for the Sewer Line
430707 - relocation work under bid item #0013.
430708 -
430709 - [On 961204 received UPRR's letter to Dutra indicating the check
430710 - was returned as a result of "complicities" Dutra discussed with
430711 - UPRR's Engineering Department, ref SDS 18 4822.]
430713 - ..
430714 - COE has directed Dutra to perform this work in accordance with the
430715 - contract requirements to obtain a permit from UPRR, ref SDS 4 5739,
430716 - and is confirming such instruction in response to Dutra's letters,
430717 - including its serial letter #0177 dated 961014 received at the
430718 - Progress Meeting on 961015. ref DRP 3 0000
430719 -
430720 - [On 961024 COE issued letter #0008. ref SDS 9 8472]
430721 -
430722 -
430723 -
4308 -
SUBJECTS
RFPs Soft-Hard Polygons
Justify Increase Unit Price
4504 -
450501 - ..
450502 - Hard/Soft Polygons Proposal - Dutra to Submit Justification for Audit
450503 -
450504 - Dutra asked about the form of the cost breakdown COE requires in order
450505 - to evaluate the 4 proposals for this matter.
450506 -
450507 - Monti Jaggers advised Dutra's price must track to the contract pay
450508 - items for the work to be performed, as set out in COE letter to Dutra
450509 - dated 961003, ref DIP 3 line 26. This instruction was conveyed at the
450510 - 960920 meeting, ref SDS 1 line 109.
450511 -
450512 - [See review COE Team at ref SDS 7 line 192.]
450514 - ..
450515 - Dutra's proposal should show the cost per cubic yard of dredging where
450516 - it has encountered hard material shown in the plans to be soft, and it
450517 - must show a justification for any amount of such cost that exceeds the
450518 - cost of performing comparable work under other pay items at other
450519 - locations in the project. This will permit the government to pay the
450520 - contractor for hard material actually encountered that was shown to be
450521 - soft, at an equitable price, as shown in the notes for the meeting
450522 - with Dutra on 961001, ref SDS 2 line 340.
450523 -
450524 -
450525 -
450526 -
4506 -
SUBJECTS
Disposal at Galbraith
Waste Discharge Requirements for Galbraith
4704 -
470501 - ..
470502 - Dutra Has Improved Effluent Process
470503 -
470504 - Rob Andrews asked about reports of effluent solids relative to
470505 - contract objectives.
470506 -
470507 - Phil Torres reported that some test readings were taken during periods
470508 - when the weirs were closed and effluent operations were actually NOT
470509 - underway. There seemed to be discussion of high wind conditions
470510 - giving skewed readings.
470512 - ..
470513 - Such conditions may distort the meaning of the readings relative to
470514 - achieving contract objectives.
470516 - ..
470517 - Phil indicated Dutra has subsequently revised its operation to ensure
470518 - the effectiveness of future testing in measuring the condition of the
470519 - completed work, as contemplated by the contract. Every adverse
470520 - condition cannot be foreseen; however, the report today indicates the
470521 - Contractor is making good progress in performing this requirement.
470523 - ..
470524 - Bob Johnston suggested that Phil submit details for the record on when
470525 - tests were done that were not representative, as discussed today.
470526 -
470527 - [See Action Item review meeting item #20, ref SDS 17 line 194.]
470528 -
470529 -
4706 -
SUBJECTS
Variations in Estimated Quantities
Surveys Predredge, Postdredge
Quantity Surveys for Payment
Shoaling, Polygon IC 3,4
5406 -
540701 - ..
540702 - Project Wide Survey - Will Be Completed End of Next Week
540703 -
540704 - Rick Olejniczak reported the survey work by G.B. Star Company is
540705 - 99% complete.
540706 -
540707 - Bob Johnston advised that Dutra cannot pay G.B. Star for survey work
540708 - as a result of a cash flow problem.
540709 -
540710 -
540711 -
5408 -
SUBJECTS
Disposal at Sonoma Baylands
Sonoma Baylands Disposal Requirements
5604 -
560501 - ..
560502 - Sonoma Baylands Levee Breach NTP Issued
560503 -
560504 - Leonard SooHoo confirmed the breaching ceremony is scheduled for
560505 - Friday, 961025 at 1230.
560506 -
560507 -
560508 -
5606 -
SUBJECTS
Remove Electrical Line in OC-4B-5
5704 - ..
570402 - ..
570403 - Leonard SooHoo and Bob Johnston are still planning to meet to discuss
570404 - the electrical cable RFP.
570405 -
570406 -
5705 -