DIARY: December 5, 1994 08:16 AM Monday;
Rod Welch
Reviewed and correct Gold Hill schedule.
1...Summary/Objective
..............
Click here to comment!
CONTACTS
0201 - PG&E Building & Land Svcs. 415 973 8273 fax or 800...
020101 - Mr. Buck Jones; =415 973 5874 mobile 415 699 2526; Land Department
SUBJECTS
Gold Hill Horseshoe Upgrade
Schedule & Budget, Update 941121a
Cost & Schedule Impacts
Schedule Files, Review
Determine Procedures
Public Meetings
Apply GO 131-D Results
0809 - ..
0810 - Summary/Objective
0811 -
081101 - Followed up work at ref SDS 20 line 64, and work at ref SDS 17 line
081102 - 98. Made a correction that seems to be needed per analysis below.
081103 -
081104 -
081105 -
0812 -
0813 -
0814 - Analysis
0815 -
081501 - The Schedule note for task HFPF Public Meetings, says it is connected
081502 - to task JP Apply GO 131-D Results. However, the Schedule itself does
081503 - not show this link, and ref SDS 17 line 98, says the Public meeting
081504 - task is no longer connected to JP, however, there is no rational set
081505 - out in the record for omitting this link. The analysis does not seem
081506 - to justify this. My view today is that we should show some influence
081507 - from GO 131-D on the Engineering process, which is the purpose of task
081508 - JP.
081509 -
081510 - Therefore, today I added this relationship back in the Schedule that
081511 - assumes we get exemption from GO 131-D requirements, ref OF 1.
081512 -
081513 -
081514 -
0816 -
Distribution. . . . See "CONTACTS"