S U M M A R Y


DIARY: November 28, 1994 01:24 PM Monday; Rod Welch

Visited Bob Masuoka on CDWR GO 131-D progress.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Building & Land Svcs.         415 973 8273 fax or 800...
020101 - Mr. Robert Masuoka, P.L.S.
020102 - Senior Land Project Analyst Room 2027, Mail Code H21A =415 973 8273
020103 - Land Department

SUBJECTS
Gold Hill Horseshoe Upgrade
Schedule & Budget, Update 941121a
Cost & Schedule Impacts
Implement Plan

0506 -    ..
0507 - Summary/Objective
0508 -
050801 - Followed up work at ref SDS 3 line 63.  I gave Bob the schedule for
050802 - Gold Hills Horseshoe, and reviewed with him the GO 131-D network.
050803 - He indicated the public review process may be shorter on CDWR.
050804 -
050805 - I delivered the schedule to 123 Mission to give ref DIP 3 line 34, to
050806 - Buck.  Buck was not in, so I called for Bob in order to get into the
050807 - building and get the thing delivered.  Bob came down and so we talked
050808 - about GO 131-D.  He said progress on GO 131-D work is going well, and
050809 - he expects PG&E can commence work on 950302, per schedule. Bob said
050810 - he has developed a network showing the tasks and sequencing to
050811 - perform GO 131-D requirements.  I asked if I could see this to
050812 - incorporate into the project schedule.
050813 -
050814 - He escorted me upstairs to his office.  Bob showed me a hand sketch
050815 - of a network he prepared showing steps needed on CDWR to carry out
050816 - PG&E's understandings of the requirements.  This was very rudiment-
050817 - ary, about 4 tasks with no durations or relationships to other parts
050818 - of the work. Bob explained a number of subsidiary steps, including
050819 - coordination among PG&E functional departments (e.g. Law, Public
050820 - Relations, Rates,...).  It was my impression that these steps are not
050821 - fully grasped in their broad implications for project impact.
050822 -
050823 -
050824 -
050825 -
0509 -
0510 -
0511 - 1402 visited with Bill
0512 -
051201 - Explained discussion with Bob.  Bill feels it would be helpful for us
051202 - to work with Bob on capturing all of the understandings about GO
051203 - 131-D and other Land issues re activities, sequencing and durations.
051204 - This will provide a better understanding by Bob and the project team
051205 - on impacts and show where attention is needed in order to reach
051206 - objectives.
051207 -
051208 -
051209 -
Distribution. . . . See "CONTACTS"