THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700
S U M M A R Y
DIARY: November 4, 1994 01:43 PM Friday;
Rod Welch
Received follow up on GH Upgrade, SMUD use of right of way.
1...Summary/Objective
2...GO 131-D Exemption NOT Needed
..............
Click here to comment!
CONTACTS
0201 - PG&E Transm Contracts 415 973 3872 fax 972 0871
020101 - Ms. Pam Taheri,; Contract Manager, Rm 2334 Mail Code B23A =415 973 1660
020102 - Transmission Contracts =415 972 0871 (fax)
0202 - PG&E Law Department 415 973 nnnn fax or 800...
020201 - Mr. Glenn West Jr., Esq.; =415 973 2776
SUBJECTS
Goldhill Horseshoe Transmission Upgrad
Contract, Develop Terms
GO 131-D
Interim Payment Agreements
1106 - ..
1107 - Summary/Objective
1108 -
110801 - Followed up work at ref SDS 3 line 292 and discussions at ref SDS 4
110802 - line 61, Received ref DRT 1 line 10 today via EM. Also talked to
110803 - Glenn West on the way back from Bob Masuoka's office. Cynthia and I
110804 - saw him in the elevator lobby. He said they decided not to write a
110805 - letter to advise of prospective additional costs arising from GO 131-D
110806 - issues.
110807 -
110808 - GO 131-D Exemption NOT Needed
110809 -
110810 - Pam's letter today indicates ref DRT 1 line 25, that following the
110811 - meeting on Wednesday, 941102, Buck Jones has reported that...
110812 -
110813 - ...it seems like we will have to go through a complete "131
110814 - D" process as to the relocation, since the 12/31/95
110815 - exemption date is unrealistic for this project.
110816 -
110817 - The reconductoring phase, however, is exempt under GO 131-D
110818 -
110819 - This would seem to change the perspective about expediting
110820 - PG&E's work in order to qualify for GO 131-D exemption on
110821 - relocating the line, per Buck's comments at ref SDS 3 line 244.
110822 - In turn, this may obviate the need for seeking agreement by
110823 - Sierra to make payments for expediting engineering in advance of
110824 - having a signed contract and project approval from PG&E
110825 - management, which was contemplated at the Progress Meeting on
110826 - 941102 at ref SDS 3 line 289.
110827 -
110828 - [See follow up at ref SDS 5 line 180, analysing EM dated
110829 - 941115 from Buck urging that PG&E obtain approval from Sierra
110830 - to finance efforts to qualify for GO 131-D exemption.]
110831 -
110832 -
110833 -
110834 -
1109 -
SUBJECTS
Goldhill Horseshoe Transmission Upgrad
941103 PG&E team in SF, Progress Meeting
1205 - Summary/Objective
1206 -
120601 - Followed up work at ref SDS 4 line 51, and at ref SDS 3 line 59.
120602 - Reported and analysed results of meetings.
120603 -
120604 -
1207 -
Distribution. . . . See "CONTACTS"