DIARY: November 1, 1994 05:07 PM Tuesday; Rod Welch

Got new project assignment for Goldhill Horseshoe Transm. Upgrade.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Proj Mngmnt Transm Sys        415 973 6778 fax 8426
020101 - Mr. Bill DeHart, PMP
020102 - Project Manager, Room 1183B-V11C =415 973 5655 pger 510 810 3026
020103 - Project Management Group

SUBJECTS
Goldhill Horseshoe Transmission Upgrad
Contract, Develop Terms

0504 -    ..
0505 - Summary/Objective
0506 -
050601 - Followed up discussions at ref SDS 1 line 153. Bill asked me to
050602 - attend a meeting tomorrow on this project.  It is in contract
050603 - development stage.  The client is Siera Pacific. Contract amount is
050604 - approx. $3.3M.
050605 -
050606 - PG&E is upgrading its transmission system to handle larger capacity
050607 - for future growth by a developer.
050608 -
050609 - Need to set up subjects and contacts with Cynthia.
050610 -
050611 -    I initially used the CDWR format to create a baseline SI, but it
050612 -    will have to be edited.
050613 -
050614 -
050615 -
050616 -
050617 -
0507 -