THE WELCH COMPANY
440 Davis Court #1602
San Francisco, CA 94111-2496
415 781 5700


S U M M A R Y


DIARY: October 24, 1994 07:31 AM Monday; Rod Welch

Review with Bill progress on CDWR activities.

1...Summary/Objective


..............
Click here to comment!

CONTACTS 
0201 - PG&E Proj Mngmnt Transm Sys        415 973 6778 fax 8426
020101 - Mr. Bill DeHart, PMP
020102 - Project Manager, Room 1183B-V11C =415 973 5655 pger 510 810 3026
020103 - Project Management Group

SUBJECTS
PM PG&E Contract - Lori Brown
Pipeline coating integrity
Pipe insulation
CDWR submit information for induction study
PG&E submit induction study
Schedule meeting

1008 -    ..
1009 - Summary/Objective
1010 -
101001 - Followed up work at ref SDS 17 line 70.  Bill said the meeting went
101002 - well.  Maria has the report nearly complete and it shows the
101003 - transmission line can be constructed within currently planned
101004 - alignment without excessive induced current onto the pipeline.
101005 -
101006 - I recommended they meet with Maria again in advance of the meeting
101007 - with CDWR to see the report in final form.
101008 -
101009 -
1011 -

SUBJECTS
Interface with CDWR Activities
Pipeline Reach No. 1, by CDWR
Switchyards, CDWR task #24

1306 - Summary/Objective
1307 -
130701 - Bill submitted photographs he has taken recently showing the pipeline
130702 - construction seems to be progressing sufficiently for PG&E to begin
130703 - construction on the transmission line in 950203, as currently planned.
130704 -
130705 -     [See follow up site inspection at ref SDS 18 line 291.]
130706 -
130707 -
130708 - He said the plant sites still show minimal work.  It is unclear
130709 - however, this relates to the task #8 on CDWR's schedule, called:
130710 -
130711 -               Three Plants - Initial
130712 -
130713 -
130714 -
130715 -
130716 -
130717 -
Distribution. . . . See "CONTACTS"