DIARY: September 25, 1994 09:41 PM Sunday;
Rod Welch
Revised schedule on PG&E CDWR project from meeting in Sacremento.
1...Summary/Objective
..............
Click here to comment!
CONTACTS
SUBJECTS
Coastal Branch Aquaduct, CDWR
Interface with CDWR Activities
Delays, General, CDWR Schedule
940923
Pipeline Reach No. 1, by CDWR
Procure Bill of Materials
Purchase Bill of Materials
0809 - ..
0810 - Summary/Objective
0811 -
081101 - Followed up work at ref SDS 15 line 80. Want to make same changes to
081102 - Casmalia WBS that were made for Arco - Polonio Pass and SLO Hydro.
081103 -
081104 - Added task GH0D0L to purchase bill of materials for transfer trip at
081105 - SLO Hydro, per note at ref SDS 15 line 247.
081106 -
081107 - Added task GH0H0L to purchase bill of materials for installing relays
081108 - at Santa Maria Substation.
081109 -
081110 - Made same changes to Casmalia of releasing construction of the
081111 - transmission line from completion of the switchyards and making the
081112 - plant operational, as was done for Arco - Polonio and SLO Hydro, ref
081113 - SDS 15 line 250.
081114 -
081115 - Restored the completion date of 960205 shown in PG&E's schedule
081116 - preapred on 940817, ref OF 1, submitted to CDWR at the project
081117 - meeting in Sacremento on 940818.
081118 -
081119 - PG&E expects it may be able to reduce the construction period to
081120 - meet the contract completion date [see later discussion at ref SDS
081121 - 16 line 177.]
081122 -
081123 -
081124 -
081125 -
081126 -
081127 -