DIARY: September 19, 1994 01:37 PM Monday; Rod Welch

Reviewed schedule adjustment CDWR with Bill.

1...Summary/Objective

ACTION ITEMS.................. Click here to comment!

1...Showed Bill the Notes created for each task. He will review these

CONTACTS 

SUBJECTS
Coastal Branch Aquaduct, CDWR
Interface with CDWR Activities
Delays, General, CDWR Schedule
Construct

0906 -    ..
0907 - Summary/Objective
0908 -
090801 - Followed up work at ref SDS 5 line 49.  Bill approved the changes
090802 - made per discussion this morning, and at
090803 -
090804 - He asked to remove the lag on tasks DH2D and DH2H, from Engineering.
090805 -
090806 - Showed Bill the Notes created for each task.  He will review these
090807 - later today to make sure they reflect his understanding of scope and
090808 - any complex or subtle rationale for creating the sequencing and
090809 - durations shown.