S U M M A R Y
DIARY: September 4, 1994 09:25 AM Sunday;
Rod Welch
Completed notes of meeting with CDWR in Stockton.
1...Summary/Objective
..............
Click here to comment!
CONTACTS
SUBJECTS
Report on Meetings/Understandings
940901 CDWR in Stockton, Communications
0404 - ..
0405 - Summary/Objective
0406 -
040601 - Followed up work at ref SDS 6 line 28. Entered notes from meeting in
040602 - Stockton on the communications issues, which was the main purpose of
040603 - meeting.
040604 -
040605 - Logged Jivat's memo to Bill, ref DRP 1 line 11, actually received at
040606 - ref SDS 2 line 38, showing PG&E submitted oa 940823 information
040607 - requested by CDWR at the meeting in Sacramento on 940818, on transfer
040608 - trip system requirements. Jivat's notes were incorporated into the
040609 - meeting notes for 940818, per ref SDS 2 line 62.
040610 -
040611 -
040612 -
0407 -
SUBJECTS
Subject Index
Subjects Create
0605 - Summary/Objective
0606 -
060601 - Have a situation where a new set of subjects seems to have appeared
060602 - for Land to obtain EIR and easements for the communication line that
060603 - supports the transfer trip system at SLO Hydro plant.
060604 -
060605 - There could also be a permitting and cost situation, where it
060606 - appears that CDWR has not made provision for this work in their
060607 - main project design.
060608 -
060609 - We need subjects for design, scheduling,
060610 -
060611 - Decided for now to just create the tasks for easements, since
060612 - basically, CDWR seems to be doing all of this work. PG&E's main
060613 - concern is to get the tasks that CDWR need to perform integrated into
060614 - PG&E's project schedule.
060615 -
060616 -
060617 -
060618 -
060619 -
0607 -