DIARY: May 18, 1992 07:14 AM Monday;
Rod Welch
Called Wayne on Broadwater management and claims; billing.
1...Summary/Objective
2...Voith's Tender
.....Objective
3...Legal Strategy
.....Legal Specialist
4...Temporary Sun Pinion Gear
.....Target Dates
.....Other Vendors
5...Power Waiting on DNRC
.....Engineer's Determination
.........Pending Issues
.........1...Did Voith comply with the contract submittal requirements
6...Bonding Company/Termination
7...Fixing CPU #6 Tape Drive
..............
Click here to comment!
CONTACTS
0201 - Dep Natrl Rscrs & Consvn 406 444 6699 fax 6721
020101 - Ms. Sarah Ann Bond, Esquire
020102 - Department Counsel =406 444 6660; Legal Division
0202 - Dep Natrl Rscrs & Consvn 406 444 6699 fax 6721
020201 - Mr. Wayne Wetzel
020202 - Director's Office
0203 - Dep Natrl Rscrs & Consvn 406 444 6699 fax 6721
020301 - Mr. Jack Zanto
020302 - Data Processing Bureau Computer Engineer =406 444 6715
020303 - Centralized Services Division
SUBJECTS
Broadwater Project
Welch Assignments,
Management Assistance Broadwater Contract
Strategy on Evaluating all Claims
Jeff Ghilardi
DNRC Legal - general views (meetings)
SDS as part of job record
Ideas, Methods, Evaluation
0910 - ..
0911 - Summary/Objective
0912 -
091201 - Broadwater Management and Claims Strategy
091202 -
091203 - Advised Wayne that Sarah asked me to call her this morning about
091204 - the Welch Assignment situation. I will talk to her about it and
091205 - asked Wayne that he try to talk to her later today so we can decide
091206 - this issue.
091207 -
091208 -
091209 - Voith's Tender
091210 -
091211 - Today, I reviewed DNRC's analysis dated May 4, 1992 of Voith's
091212 - "Tender" to DNRC, ref DIP 1.
091213 -
091214 - My initial reaction is that Voith's offers are inadequate in
091215 - seeking additional compensation to repair the defective speed
091216 - increaser, without offering any justification. Voith has not yet
091217 - been directed by the Engineer to fix the plant and has not yet been
091218 - faced with a notice to terminate.
091219 -
091220 - Their offer seems intended to move the parties away from
091221 - the terms of the contract in so Voith can later claim the
091222 - contract was abandoned and therefore should not govern
091223 - DNRC's entitlement to recover on its claims.
091224 -
091225 - Ordinarily a contractor should only be paid on the basis of
091226 - performance. If Voith cannot finance its own corrections,
091227 - how will it pay for an award to DNRC in an arbitration, as
091228 - contemplated by Voith's offer.
091229 -
091230 - An arbitration will require at least 6 months and probably
091231 - several years to settle.
091232 -
091233 - The purpose of a bond is insurance to obtain performance.
091234 -
091235 - The money being sought by Voith is not nearly enough to fix
091236 - the plant (what about the punch list stuff, which will
091237 - approach $.5M plus). DNRC will pay out money and still not
091238 - get ultimate performance.
091239 -
091240 -
091241 - Has DNRC researched its entitlement under Voith's performance bond
091242 - and concluded there is a reason for providing additional payment to
091243 - Voith in order to induce them to perform? Has Voith brought some
091244 - evidence forward that shows DNRC is liable to Voith for extra
091245 - compensation to fix the defective speed increaser and other plant
091246 - punch list items?
091247 -
091248 - Voith has shown no ability to perform to date; what evidence is
091249 - there that if DNRC accepts any of these offers that Voith will
091250 - perform now?
091251 -
091252 -
091253 -
0913 -
0914 -
0915 - 0823 called Sarah
0916 -
091601 - Faye answered. She said Sarah is at the copy machine. Faye will let
091602 - her know I called.
091603 -
091604 - Objective
091605 -
091606 - Review issues at ref SDS 2 line 091258 and above.
091607 -
091608 - Do they want claims preparation per ref DIP 1 line 56?
091609 -
091610 -
091611 -
091612 -
091613 -
0917 -
0918 -
0919 - 1240 called Wayne
0920 -
092001 - Legal Strategy
092002 -
092003 - He said Power has requested a statement of legal "strategy" from DNRC
092004 - relative to issuing a directive to Voith to perform. Wayne has asked
092005 - Sarah to prepare a memo on it which she worked on over the weekend.
092006 -
092007 - He said Sarah was concerned that the issues are "...too fact
092008 - specific," but that she could do a generic memorandum opinion on
092009 - strategy. This position seems unclear in light the project record
092010 - with respect to the parties duties and rights (however, it would help
092011 - to have some "Engineer's Determinations" on Voith's performance, per
092012 - analysis below). Wayne indicated he asked Sarah to produce what she
092013 - feels is an appropriate analysis.
092014 -
092015 - Legal Specialist
092016 -
092017 - I explained that developing a legal strategy memo is a very
092018 - difficult assignment that will require several iterations, and
092019 - suggested that DNRC be sensitive to the possibility that support
092020 - may be needed on this task.
092021 -
092022 -
092023 - Temporary Sun Pinion Gear
092024 -
092025 - Wayne indicated Power has issued a directive to Voith to install a
092026 - temporary "sun pinion" gear until the speed increaser is fixed, but
092027 - the directive does not have any interim target dates.
092028 -
092029 - DNRC is doing this to "mitigate" damages relative to the risk of a
092030 - failed speed increaser.
092031 -
092032 - Target Dates
092033 -
092034 - I encouraged DNRC to give Voith some specific milestones for Voith
092035 - to reach in the near term to demonstrate good faith performance.
092036 - Voith should be required to change PM's, list project personnel
092037 - and submit a CPM within 2 weeks (similar to what was done with
092038 - Tudor's termination scenerio).
092039 -
092040 - Thereafter, Voith must show compliance with CPM completion dates.
092041 -
092042 - Other Vendors
092043 -
092044 - If DNRC is going to pay out more money, consideration should be
092045 - given to taking over the work, so Voith does not spend the funds
092046 - on other things and to insure a competent result.
092047 -
092048 -
092049 - ..
092050 - Power Waiting on DNRC
092051 -
092052 - Wayne advised that Power has indicated it cannot direct Voith to
092053 - perform the contract until Sarah produces a legal strategy.
092054 -
092055 - Engineer's Determination
092056 -
092057 - Called Wayne back. He did not have time to discuss this in depth,
092058 - but I mentioned that Power's representation to DNRC that Power
092059 - cannot issue Engineer's Determinations until Sarah completes a
092060 - legal strategy, requires careful analysis.
092061 -
092062 - I explained that generally this is incorrect. Legal strategy
092063 - evolves in large part from facts. The Engineer determines facts.
092064 - Thus, some measure of concurrent effort by the Engineer to deter-
092065 - mine the following factual issues would support the analysis of
092066 - legal strategy:
092067 -
092068 - Pending Issues
092069 -
092070 - 1. Did Voith comply with the contract submittal requirements
092071 - and were deviations accepted as contract changes orders,
092072 - or merely overlooked by Tudor.
092073 -
092074 - If Tudor changed the requirements, when, by what
092075 - instrument and authority and for what consideration?
092076 -
092077 - 2. Is the contract substantially complete, incomplete or
092078 - complete and as a result which presumed damages provisions
092079 - apply?
092080 -
092081 - Did Tudor change the requirements for contract
092082 - completion, and if so when, by what instrument and
092083 - authority and for what consideration?
092084 -
092085 - 3. Do Voith's recent SI submittals meet the contract.
092086 -
092087 - 4. Has Voith has made adequate progress in performing the
092088 - work?
092089 -
092090 - 5. Is any of the work is defective?
092091 -
092092 - 6. What is the current contract amount, as amended.
092093 -
092094 -
092095 -
092096 - I recommended that DNRC consider asking the Engineer to determine the
092097 - above issues and others related to Voith's performance of its contract
092098 - obligations, since ultimate findings of fact will be influenced by the
092099 - Engineer's determinations. Expert claims analysis may be needed for
092100 - the Engineer to make the above determinations.
092101 -
092102 -
092103 -
092104 - Bonding Company/Termination
092105 -
092106 - Wayne indicated that DNRC has not contacted Voith's bonding company,
092107 - however they have provided copies of some correspondence on pertinant
092108 - issues.
092109 -
092110 - Wayne recalled that Sletten's bonding company was not helpful during
092111 - the period when DNRC was considering terminating Sletten.
092112 -
092113 - I explained the bonding company and contractor must both be served
092114 - a demand for performance in order to find out what they will do.
092115 - Suggested someone call the bonding company to alert them that DNRC
092116 - is serious and give them an opportunity to encourage Voith to
092117 - perform.
092118 -
092119 - This another area where outside counsel could be helpful in
092120 - advising DNRC.
092121 -
092122 -
092123 -
0922 -
0923 -
0924 - Sarah called back
0925 -
092501 -
092502 -
092503 -
092504 -
092505 -
092506 -
092507 -
0926 -
SUBJECTS
Broadwater Project
Loan to DNRC to Evaluate SDS, 920304
Develop & Maintain Hardware System
SDS support for DNRC (network)
1207 - Summary/Objective
1208 -
120801 - Fixing CPU #6 Tape Drive
120802 -
120803 - Advised we need to get Jack or Mike to call Everex today and see if
120804 - they can do some diagnostics over the phone. Wayne asked me to call
120805 - Jack and coordinate with him.
120806 -
120807 -
120808 -
1209 -
1210 -
1211 - 0905 called Jack
1212 -
121201 - He is out until 1020 their time, or in about 10 minutes. Left
121202 - message for Jack to call back.
121203 -
121204 -
121205 -
1213 -
1214 -
1215 - 1020 Jack called back
1216 -
121601 - He said he spoke to Wayne and advised him that his work schedule is
121602 - tied up for 2 weeks on installing a network system. He cannot work
121603 - on either the tape drive matter or set the irq for the modem.
121604 -
121605 -
121606 -
1217 -
Distribution. . . . See "CONTACTS"