S U M M A R Y
DIARY: January 9, 1992 11:34 AM Thursday;
Rod Welch
Respond to memo from DNRC on Welch assignment scope.
1...Summary/Objective
2...Analysis of DNRC Memo on Welch Assignment - ref DRP 1
3...Background on Scope of Welch Services
4...Estimated Date of Completing Analysis of pre-July 1989 Claims
....Comment
.....Tudor SF Records
.....Management Strategy
5...Welch Provided Requested Management Support
.....Comment
.....Welch Agreement Pending Amendment #02
6...Owner Oversight Essential
.....Comment
.....Oversight Skill Maintains Engineer's Responsibility
.....Engineer is Not an Advocate
.....Owner's Advocate Management Alternatives
.....Management Support Needed for Next Several Months
..............
Click here to comment!
CONTACTS
0201 - Dep Natrl Rscrs & Consvn 406 444 6699 fax 6721
020101 - Mr. Wayne Wetzel
020102 - Mr. Walt Anderson; Hydro Power Section Supervisor =406 444 6659
020103 - Engineering Bureau fax 406 444 0533
020104 - Ms. Sarah Ann Bond, Esquire
020105 - Department Counsel =406 444 6660; Legal Division
SUBJECTS
Backcharges to Voith from Sletten
General
A02 - Extend Current Contract
Analysis of Pending Tasks
Engineer's duty to determine disputes
0807 - ..
0808 - Summary/Objective
0809 -
080901 - Follow up ref SDS 13 0000.
080902 -
080903 - This reviews DNRC's Jan 8, memo on the Welch scope of work, and
080904 - recommends areas and methods of DNRC management oversight on
080905 - Broadwater needed to achieve a successful outcome.
080906 -
080907 - Sarah is scheduling a meeting with Wayne on this.
080908 -
080909 - [On 920110 met with Wayne and Sarah. ref SDS 14 0001
080910 -
080911 -
080912 -
080913 - ..
0810 -
0811 -
0812 - General
0813 -
081301 - DNRC's memo indicates the Welch support is no longer needed nor
081302 - appropriate to assist DNRC with managing Broadwater and so Welch
081303 - should complete work by Jan 17, 1992 on DNRC's claims arising from
081304 - Tudor's Oct 5, 1989 letter to DNRC.
081305 -
081306 - ..
081307 - On Dec 6, 1991 DNRC requested continued support in managing Broadwater
081308 - tasks cited at ref SDS 12 and 5. Sarah and Walt were assigned to
081309 - draft an amendment to this effect, ref SDS 10 line 051119.
081310 -
081311 - ..
081312 - I called Sarah this morning on the status of the amendment.
081313 -
081314 - She feels it should be discussed again with Wayne, per her memo, and
081315 - is scheduling a meeting. Wayne's work on the budget may put the
081316 - meeting off until Friday, Jan 10.
081317 -
081318 - This analysis can guide the discussions with Wayne.
081319 -
081320 -
081321 -
081322 - ..
081323 - Analysis of DNRC Memo on Welch Assignment - ref DRP 1
081324 -
081325 - This is a document dated Jan 8, 1991, but it is intended to be
081326 - for Jan 8, 1992 and so has been entered as such. To facilitate
081327 - references, I entered the document and will use the line numbers in
081328 - ref DRP 1.
081329 -
081330 -
081331 - ..
081332 - Background on Scope of Welch Services
081333 -
081334 - DNRC's memo of Jan 8, states at line 13:
081335 -
081336 - This is to confirm our earlier discussions (both between you and me
081337 - and among Wayne, you and me) about the scope of services requested
081338 - to be performed by Welch Co. for the Department.
081339 -
081340 -
081341 -
081342 - ..
081343 - Estimated Date of Completing Analysis of pre-July 1989 Claims
081344 -
081345 - DNRC's memo of Jan 8, requests "...a draft final analysis" by Jan 17,
081346 - 1992 and to advise DNRC if such date is not feasible.
081347 -
081348 - Comment
081349 -
081350 - I met with Sarah on Dec 16, 1991, per ref SDS 2 and received her
081351 - comments on the claim analysis submitted to DNRC on Oct 31, 1991,
081352 - ref DIP 1. Based on the issues and scope of remaining work we set
081353 - a follow up target date for the end of January 1992, as follows:
081354 -
081355 - Welch will work on this matter as time permits relative to
081356 - other support tasks with the objective of submitting these
081357 - claims to Voith by the end of January 1992. This may be
081358 - delayed if Welch is involved in the meetings on interviewing
081359 - engineers, hiring and transitioning operations. (ref SDS 11
081360 - line 061317).
081361 -
081362 - ..
081363 - I expect a final claim report on these matters could be produced by
081364 - the end of January, 1992 or early February, as contemplated at the Dec
081365 - 16 discussions. If a particular completion date is essential,
081366 - overtime could be applied.
081367 -
081368 - ..
081369 - Tudor SF Records
081370 -
081371 - This further assumes information needed from the Tudor main office
081372 - records is available, or that the information needed to show
081373 - DNRC's entitlement is at the Helena office.
081374 -
081375 - I am hopeful all of the information needed is in the Tudor
081376 - Broadwater records.
081377 -
081378 - ..
081379 - Management Strategy
081380 -
081381 - DNRC should consider whether it is prudent to submit a series of
081382 - complex claims to the Engineer or Voith at the present time, or
081383 - whether it might be better to do so after resolving pending design
081384 - and construction issues.
081385 -
081386 - ..
081387 - The current schedule, ref DIP 2, shows the Engineer will begin
081388 - considering claims formally on or about April 1, 1992, after
081389 - resolving speed increaser matters, completing review of the
081390 - contract, reading into the job and publishing an initial report to
081391 - DNRC on the status of the project. At some point the Engineer
081392 - should prepare its own schedule, but at this juncture DIP 2 is the
081393 - only guidance on this matter.
081394 -
081395 -
081396 -
081397 - ..
081398 - Welch Provided Requested Management Support
081399 -
081400 - This issue was addressed at ref SDS 6 - 4 in October and more recently
081401 - on Dec 6, per ref SDS 10 DNRC's Jan 8, 1992 memo states at line 21:
081402 -
081403 - As the [Engineer] selection process is complete, you are requested
081404 - to devote your primary attention to the pre-1989 claims. Also, we
081405 - request you be available to Dave O'Day, the new project manager,
081406 - to answer his questions that arise while he is familiarizing him-
081407 - self with the project.
081408 -
081409 - ..
081410 - Comment
081411 -
081412 - I advised the DNRC Director on Nov 22, there would be a lot of
081413 - work to do to hire a new Engineer and get them up to speed. Since
081414 - then, DNRC staff have work hard on this matter, yet much remains
081415 - to be done to conclude a viable Agreement with Power, see ref SDS
081416 - 1, 12 and 13.
081417 -
081418 - ..
081419 - There is no record indicating that DNRC's objectives will be met
081420 - by Power. No reports, determinations or analyses have been issued
081421 - by Power that show its work product will yield a better result
081422 - than Tudor accomplished. DNRC believes Tudor did not perform, but
081423 - can only cause Power to do better through assiduous oversight.
081424 -
081425 - DNRC's interest in obtaining a favorable outcome then augurs for
081426 - greater attention to:
081427 -
081428 - 1. Formulating the Agreement with Power.
081429 -
081430 - 2. Transitioning and developing Power's assumption of the
081431 - Engineering duties under the Voith Contract.
081432 -
081433 - 3. Oversight and coordination of Engineer and DNRC to
081434 - accomplish project objectives.
081435 -
081436 -
081437 -
081438 - ..
081439 - Welch Agreement Pending Amendment #02
081440 -
081441 - The discussion of Dec 6, 1991 showed DNRC recognized the above
081442 - points (see ref SDS 10 line 0510), in that:
081443 -
081444 - Sarah indicated the Legal Division has the [claim] analyses it
081445 - needs from Welch for the time being, and now needs a month to
081446 - absorb it without more coming it. [Therefore Welch would not
081447 - be needed in January, 1992].
081448 -
081449 - ..
081450 - Wayne said that he believes DNRC needs support by Welch for
081451 - hiring and managing a new Engineer, advising the Department on
081452 - the Tudor and Voith matters and creating the SDS record that
081453 - protects DNRC's interests.
081454 -
081455 - ..
081456 - Wayne asked what specific tasks are needed to accomplish these
081457 - objectives? I cited the tasks listed in the memo of Dec 4,
081458 - 1991 requested by Sarah, which sets out the scope for
081459 - amendment #2 to the Welch Agreement with DNRC.
081460 -
081461 - ..
081462 - Wayne asked if the Dec 4 memo was discussed with Walt? The
081463 - memo was distributed to Walt and Rick, per ref SDS 7, and I
081464 - discussed it with Walt this morning. He commented that there
081465 - is a lot to do.
081466 -
081467 -
081468 - Wayne asked Sarah to meet with Walt and work on an amendment
081469 - to extend Welch's contract. This will be amendment #2.
081470 -
081471 -
081472 -
081473 - ..
081474 - Owner Oversight Essential
081475 -
081476 - DNRC's Jan 8, 1992 memo contends it would be improper for DNRC to
081477 - obtain help from Welch in managing its Engineer:
081478 -
081479 - It would be inappropriate for the Department to assign [Welch]...
081480 - to manage our project engineer. This is not to indicate that
081481 - Welch Co.'s services are not valuable, but rather that the proper
081482 - procedure, as you point out in your diary report of January 7,
081483 - 1992, line 071320, is for Power to provide the management and
081484 - engineering services, not the Department.
081485 -
081486 - ..
081487 - Comment
081488 -
081489 - A conclusion that DNRC should not obtain competent assistance on
081490 - oversight of the Broadwater project, especially a new Engineer, is
081491 - different from the intent of the Jan 7, diary report (ref SDS 1)
081492 - which states in part at line 071320:
081493 -
081494 - ..
081495 - I think the trick is to place the burden on Power to figure
081496 - out the expertise it needs after fully explaining the objec-
081497 - tives, issues and background. We cannot completely explain
081498 - the background and all of the nuances of the issues in time
081499 - for the Jan 14, meeting though. The memo, ref DIP 1, seeks to
081500 - get Power into the subject and indicate other related informa-
081501 - tion which Power may wish to examine.
081502 -
081503 - ..
081504 - Clearly DNRC can hold its Engineer responsible to perform its
081505 - duties and at the same time DNRC can be looking to see that the
081506 - Engineer in fact performs such duties correctly, provided such
081507 - oversight is done correctly.
081508 -
081509 - ..
081510 - The record on Broadwater shows DNRC has been improperly pressured
081511 - to perform or waive tasks which were the responsibility of its
081512 - Engineer and contractors. Some of this was overt; much was simply
081513 - negligence in that the managements involved though nominally com-
081514 - petent, overlooked details or lacked the experience to recognize
081515 - and treat critical details. The job was managed by conversation.
081516 - DNRC should not permit this mistake to be repeated.
081517 -
081518 - ..
081519 - Since these pressures are endemic to contracting, it would seem an
081520 - appropriate and prudent step for DNRC to avail itself at this
081521 - critical juncture of the assistance it needs to recognize and
081522 - effectively resist such pressures.
081523 -
081524 -
081525 - ..
081526 - Oversight Skill Maintains Engineer's Responsibility
081527 -
081528 - There is an important skill and methodology involved in providing
081529 - owner oversight that does not supplant the Engineer's (or the
081530 - contractor's) responsibility to perform.
081531 -
081532 - Thus, the Owner should introduce the Engineer to consultants (e.g.
081533 - Geartech) and participate in actual discussions during a transi-
081534 - tion period that is sufficient to:
081535 -
081536 - 1. Assist the Engineer in understanding the background and
081537 - and implications of issues; and,
081538 -
081539 - 2. Evaluate the Engineer's performance in meeting the
081540 - owner's objectives.
081541 -
081542 - ..
081543 - In such discussions, the Owner may well be asserting facts and
081544 - contract interpretations, but at the end of the day, the
081545 - record shows the Engineer relied on his own determination of
081546 - facts and analyses.
081547 -
081548 - This requires knowledge and skill in knowing what questions to
081549 - ask, what facts to assert, what authority to cite and what
081550 - information to record. It is also helpful to have a tool like
081551 - SDS to apply the skill.
081552 -
081553 -
081554 - ..
081555 - Engineer is Not an Advocate
081556 -
081557 - DNRC has hired an Engineer to perform the duties in the Voith/DNRC
081558 - contract which require the Engineer to make impartial determin-
081559 - ations rather than advocate one position or another. If the
081560 - Engineer is compromised in this regard, then much of the benefit
081561 - of hiring an engineer to make contract determinations may be lost.
081562 - It requires management skill to preserve this posture. The
081563 - current state of the project in some respects reduces the
081564 - importance of this objective, but DNRC should strive to maintain
081565 - the cloak of impartiality where practical.
081566 -
081567 -
081568 - ..
081569 - Owner's Advocate Management Alternatives
081570 -
081571 - Owners often use construction managers for project support, where
081572 - the Engineer reports to the CM. Another scheme is for the owner
081573 - to hire an audit Engineer that periodically (usually quarterly),
081574 - reviews the project and reports to the owner on the status of the
081575 - work and recommends management improvements needed by engineer,
081576 - contractor, owner, etc.
081577 -
081578 - ..
081579 - Management Support Needed for Next Several Months
081580 -
081581 - At this time I believe full time CM is not warranted, nor is it
081582 - necessary to hire an audit engineer. However, continuing manage-
081583 - ment support is recommended for at least the next several months
081584 - to transition the Engineer and to ensure that DNRC's interests are
081585 - protected in the record with respect to its claims against Voith
081586 - and Tudor, as cited by Wayne at ref SDS 8 line 051105 (repeated
081587 - above under "Amendment to Welch Agreement").
081588 -
081589 - ..
081590 - It is understandable that the engineer and the contractor prefer
081591 - to avoid such oversight, as Tudor, Voith and Sletten preferred.
081592 - The record of the project, however, indicates that acceding to
081593 - such preference has not served the Department well. DNRC needs
081594 - more management support at least in the near term because there
081595 - are more people to manage.
081596 -
081597 - ..
081598 - Right now the new Engineer is managing by conversation. There is a
081599 - lot of talk among a lot of people that makes it seem like a lot is
081600 - getting done. DNRC knows from the past, however, that valuable
081601 - knowledge and ideas are slipping away. Conversations today that seem
081602 - to produce solutions will prove wanting, and what appears to be
081603 - inconsequential nuance, will later prove critical.
081604 -
081605 - [On 920110 Sarah concerned about Welch directing the Engineer.
081606 - ref SDS 14 0869
081607 -
081608 - ..
081609 - To get better results and avoid past mistakes, we have to do things
081610 - differently.
081611 -
081612 - ..
081613 - Sarah points out in her memo that Welch is to answer questions
081614 - proffered by Power. Leaving aside whether Power knows at this stage
081615 - what questions to ask that will advance the interests of DNRC, it is
081616 - unlikely Power or any reasonable Engineer would subject themselves to
081617 - the accountability inherent in asking Welch a question. So far Power
081618 - has not done so. Tudor did the same in April of 1989.
081619 -
081620 - ..
081621 - Only the owner can set in it place and support the management needed
081622 - to protect its interests. I urge DNRC to do so.
081623 -
081624 -
081625 -
081626 -
081627 -
081628 -
081629 -
081630 -
081631 -
081632 -
081633 -
081634 -
0817 -
Distribution. . . . See "CONTACTS"