S U M M A R Y
DIARY: September 29, 1988 05:31 PM .......;
Rod Welch
Worked on BPP on various matters.
1...Summary/Objective
2...Schedule Updated to Evaluate Contractor's Request for Time Extensions
..............
Click here to comment!
CONTACTS
0201 - Tudor Engineering Company
020101 - Mr. Jeff Ghilardi; Resident Engineer
SUBJECTS
Litigation Support
Dewatering Reliability
Standby Power System
0505 - ..
0506 - Summary/Objective
0507 -
050701 - Follow up ref SDS 2 GY9H.
050702 -
050703 - Prepared 7 day notice to Sletten on providing reliable dewatering
050704 - capability, per Norm's request yesterday. ref SDS 2 GY9H
050705 -
050706 - Prepared cover letter for Clyde and Sarah Bond for comments.
050707 - Submitted draft to them. If we don't hear by 1400, will publish as
050708 - is.
050709 -
050710 -
050711 -
050712 -
050713 -
050714 -
0508 -
0509 -
SUBJECTS
Schedule
Time Extensions
Updated Schedule
0906 -
090601 - ..
090602 - Schedule Updated to Evaluate Contractor's Request for Time Extensions
090603 -
090604 - Need to respond to Sletten's 880908 Schedule.
090605 -
090606 - Since earlier proposed response was not accepted by Tudor management,
090607 - decided to include in this thing the Engineer's position on granting
090608 - time extensions. This gives the Owner the ability to grant time
090609 - extensions when they are ultimately established, but avoid acceler-
090610 - ation expense due to lack of timely notice. The difficulty with this
090611 - is that the Owner has already acknowledged the Contractor is
090612 - accelerating pursuant to a $225 000 payment.
090613 -
090614 - Responded to Sletten's 80923 letter, ref 12 with Tudor ref 13.
090615 -
090616 - Prepared cover letter for Clyde and Sarah Bond for comments.
090617 - Submitted draft to them. If we don't hear by 1400, will publish as
090618 - is.
090619 -
090620 -
090621 -
090622 -
090623 -
090624 -
Distribution. . . . See "CONTACTS"